The No. 7 blast furnace of Jiuquan Iron and Steel Company successfully ignited and opened to present the birthday of the Party.

iconJul 1, 2020 14:50

SMM Network News: as the ignition day of No. 7 blast furnace is approaching, the optimization and upgrading project department of No. 7 blast furnace organizes, studies and formulates a detailed and detailed opening plan in advance with a high sense of responsibility and mission, and confirms and accepts each key area, every construction project, every key link and every elimination content of the opening plan one by one through the daily plan management method of "daily completion and daily high". At the same time, according to the necessary conditions for the opening of the blast furnace, multi-point efforts should be made to promote the construction of various sub-projects, and multi-parties should coordinate the production preparation before the start-up of the blast furnace to ensure the smooth start-up of the No. 7 blast furnace. (Wang Gang)

No. 7 blast furnace optimization and upgrading project blast furnace body begins to be filled with opening charge

At 05:30 on June 26th, the blast furnace body of the No. 7 blast furnace optimization and upgrading project began to fill the opening charge, indicating that the ignition target of the No. 7 blast furnace optimization and upgrading project has entered the countdown state.

The blast furnace is opened with sleepers. According to the requirements of the opening process, the hearth, waist and body of the blast furnace are filled with sleepers, clean coke, empty material and normal material in 11 sections respectively.

In order to complete the task of filling and opening charge safely, high quality and high efficiency, the project department of No. 7 blast furnace overhaul project formulates "No. 7 blast furnace sleeper filling scheme" and "No. 7 blast furnace charging scheme" according to blast furnace production technology, technical requirements, combined with opening charge, raw fuel of Jiuquan Iron and Steel Co. In order to ensure the safe filling of hearth coke and sleepers, the project department of No. 7 blast furnace overhaul project fully confirmed the working conditions such as temperature and ventilation in the furnace before the operators entered the furnace, and strictly check whether the safety protection measures of the operators are in place. In order to ensure the scientific and reasonable distribution of the opening charge, the technical staff of the project department have done many process studies, combined with the testing of the composition and physical properties of the opening material, the use of 3D scanning, radar location and other technologies to measure the blast furnace different distribution angle, distribution trajectory, material surface shape and so on, in order to provide data technical support for the follow-up distribution. In order to ensure the orderly connection of the charging, the project department is responsible to the person, arranging a special person to strictly monitor and control the charging process, to observe the charging process under the trough and to make a good record, so as to provide strong conditions for the rapid recovery of furnace condition and rapid production after opening.

It is understood that the charging of the blast furnace will be completed before June 29. (Wang Gang)

Recently, the revamping project of No. 5 steel-making crane in the rolling mill has been successfully completed and put into use, laying the foundation for realizing high steelmaking production after the resumption of production of No. 7 blast furnace.

The steelmaking 5cm crane undertakes the tasks of continuous caster billet production and finished billet outward delivery. Since it was put into operation in 2018, the crane has been used frequently, and there are some problems, such as car body deformation, end beam cracking, wheel gnawing rail and so on, so it is difficult to operate normally. For this reason, the rolling mill organizes technicians to upgrade and transform the hinged mechanism of the girder and the optimization of the connection position of the end beam.

The modified crane effectively reduces the operation failure of the equipment, ensures the safe and stable operation of the crane, and reduces the impact on production. If only the wheel is invested, the cost can be saved about 60,000 yuan in the whole year. (Hao Huibin)

Recently, the Western heavy Industry Company Honglian automatic Control Company has fully completed the installation and commissioning of the electrical equipment of the No. 7 blast furnace optimization and upgrading project, and successfully passed the acceptance inspection, providing a strong guarantee for the smooth commissioning of the No. 7 blast furnace optimization and upgrading project.

It is understood that Honglian automatic Control Company installed nearly 40 sets of electrical equipment such as water pump motor power cable, evaporative air cooler fan motor, cooling tower fan motor and other electrical equipment for the No. 7 blast furnace optimization and upgrading project. In the process of installation and debugging of electrical equipment, the installation of a lot of electrical equipment needs to clear the original cable, and then lay new cables. Installation and debugging should not only ensure that the direction and depth of the original cable trench will not be destroyed, but also ensure that the newly laid cable adapts to the specifications of the new equipment, which greatly increases the difficulty of construction.

 

In order to ensure that the installation and commissioning of the electrical equipment of the project is completed on schedule, and to achieve the expected results of automation, intelligence and informatization, Honglian automatic Control Company attaches great importance to the on-site installation work and requires all departments to cooperate closely, focusing on solving practical problems on the spot and grabbing the installation time limit. In particular, for the problem of deviation between design and practice, a reasonable optimization scheme was quickly put forward, necessary supplementary design and improvement were carried out for the lack of design, and finally all installation plans were successfully completed, which contributed to the smooth completion of the optimization and upgrading project of No. 7 blast furnace on schedule. (Zhang Zhifang)

2020 China Ni-Cr stainless Steel Industry Market and Application Development Forum

Scan the QR code, apply for participation or join the SMM metal exchange group

Stainless steel
nickel
steel
production capacity