The Power Conversion System (PCS) is key in energy storage, enabling DC to AC conversion for grid integration. As battery cell capacities increase, the demand for higher power PCS units, like the 2,500 kW models, is growing. The Shanghai Metals Market (SMM) lists prices for various PCS, including 1,725 kW and 2,500 kW centralized units, and a 215 kW string inverter. Prices for the 1,725 kW PCS are stable at 0.08 RMB/W, while the 2,500 kW units show a downward trend. String inverter PCS, designed for large systems, are priced at around 0.11 RMB/W, facing slow market adoption due to higher costs.

The Power Conversion System (PCS) is the central component of energy storage systems, responsible for managing the energy conversion and bi-directional transmission between energy storage batteries and the power grid. The primary function of the PCS is to convert Direct Current (DC) from the batteries to Alternating Current (AC) for grid use and to perform the reverse conversion when the grid supplies power to the storage system. Specifically, the PCS transforms the DC stored in the energy storage batteries into AC suitable for the power grid during energy discharge, and when the grid needs to absorb energy, the PCS converts the AC from the grid back into DC for storage in the batteries. This dual-direction energy conversion process enhances the flexibility and reliability of the power grid and supports the efficient use and optimal allocation of energy.

Currently, the Shanghai Metals Market (SMM) has published pricing information for three models of energy storage PCS on its official website. These include two centralized PCS models with capacities of 1,725 kW and 2,500 kW, respectively, and one string inverter PCS model with a capacity of 215 kW.

SMM's research indicates that centralized PCS are more widely used in utility-scale energy storage systems. With the gradual increase in energy storage cell capacity from 280Ah to 314Ah, the system's capacity has expanded from 3.4MWh to 5MWh. For example, a 2-hour energy storage system now requires a PCS with an upgraded capacity from 1,725 kW to 2,500 kW. Several PCS manufacturers in China have introduced products with a 2,500 kW capacity.

In terms of pricing, SMM's investigation reveals that the centralized 1,725 kW PCS is slightly more expensive than the 2,500 kW PCS, at approximately 0.08 RMB/W, and this price has remained stable in recent months. However, the price for the centralized 2,500 kW PCS has been trending downward, starting from around 0.08 RMB/W in early June and now ranging between 0.075 RMB/W and 0.078 RMB/W. Additionally, among the 2,500 kW centralized PCS products, Chinese manufacturers have introduced both a modular dual-branch design of 1,250 kW x 2 and a single-branch design of 2,500 kW. The price difference between these two designs is minimal, with a variance of less than 0.005 RMB/W, making the single-branch design relatively more economical.

Regarding the string inverter PCS, to accommodate the development of large-capacity energy storage systems and to achieve "one cluster, one management" for improved battery consistency and system reliability, several Chinese manufacturers have introduced various string inverter PCS products, including the 215 kW model, which is the mainstream model in terms of shipments. However, despite these advantages, the string inverter PCS is still in the developmental stage in China's energy storage market. This is due to the relatively high cost of string inverter PCS in the current competitive market environment, resulting in a less apparent cost advantage and a lower market penetration rate. SMM's recent research indicates that the price has remained stable, at about 0.11 RMB/W.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
16 hours ago
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Read More
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
On January 28th, the construction of the 500-kilovolt power transmission and transformation project in Fengtai, Beijing officially started. This project is the first newly-built 500-kilovolt power grid project in Beijing during the 15th Five-Year Plan period. It will significantly enhance the resilience and power receiving capacity of the southern Beijing power grid and provide reliable power support for Beijing to continuously optimize the investment structure and vigorously develop high-end, precise, and cutting-edge industries. The 500-kilovolt power transmission and transformation project in Fengtai, Beijing is a key project of Beijing's power grid during the 15th Five-Year Plan period and one of the "3 100" key projects in Beijing this year. It is constructed and managed by the State
16 hours ago
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
16 hours ago
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Read More
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
On February 1st, the 500-kilovolt AC system of the Hezhou Converter Station, the receiving-end station of the ±800-kilovolt UHV DC power transmission project from northern Shaanxi to Anhui, was officially put into operation after a 24-hour trial run.
16 hours ago
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
16 hours ago
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
Read More
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
On February 2nd, the 750-kilovolt power transmission and transformation project of the third passageway from northern Shaanxi to central Shaanxi was fully connected. The project starts from the 750-kilovolt Shuofang Substation in Shenmu City in the north and ends at the 750-kilovolt Bailuyuan Substation in Lantian County in the south. It has newly built a 1,271-kilometer line, passing through 18 counties (districts) in 4 cities including Yulin, Yan'an, Weinan and Xi'an.