CATL Lithium-containing China Clay Ore Beneficiation Plant Made Progress In Jiangxi    

Telah Terbit: May 30, 2023 15:55
The main construction of the first phase of the beneficiation plant in Yichun of Jiangxi is progressing smoothly. According to the information previously disclosed by CATL, the 33 million mt of lithium-containing china clay ore dressing project will be constructed in three phases.

The main construction of the first phase of the beneficiation plant in Yichun of Jiangxi is progressing smoothly. According to the information previously disclosed by CATL, the 33 million mt of lithium-containing china clay ore dressing project will be constructed in three phases.

The first phase with 10 million mt of raw ore production capacity was originally planned to be completed in early January and put into trial production in April. Previously, domestic media reported that the main body of the beneficiation plant would be completed and put into use in May.

More popular news:

Copper Shortage Is Irreparable Even after Biggest Mergers and Acquisitions, Here’s Why

Global Aluminium Inventory to Plunge Further amid Supply Headwinds, LME Aluminium Prices to React Fast

SMM Daily Comments (May 17): Most Metals prices Rose, Ferrous Metals Jumped with Coking Coal soaring 3.29%,Oil Went Down on Surprise Inventory Growth, Poor China Economic Data and IEA Doubt on Russia Cheating on Output Cuts

Testing Agency Responds to Great Wall Motor Report on BYD to Chinese Authorities

BHP Says China's Real Estate Recovery Will Boost Metals Demand

G7 to Expand Sanctions Covering Metals on Russia, Promises Further Support for Ukraine

BYD Denies Rumours after Being Reported to Chinese Authorities, Two Top China Automakers Escalate War

Trafigura Sees Copper Prices Rising to All-Time High on China Economic Rebound and Supply Shortages

The Ban will Not Stop Exports of Key Raw Minerals Copper, Zinc, Iron Ore from Indonesia, But Bauxite Shipments will Stop in June

SMM Daily Comments (May 24): LME Base Metals Closed with Losses, All Ferrous Metals Dropped with Iron Ore Plunging, Oil Gained Ground as Goldman Sachs Sees Stubborn Shortage from June

High Lithium Ore Prices in Australia will Drive Lithium Prices Rebound, Reasons Prevent Output to Grow

A Bull Gold Market Has Just Begun 

Global Key Base Metals Face Supply Glut, Severe Oversupply for Aluminium, But There Is a Global Copper Shortage

Goldman Sachs Warns of Serious Risks US Dollar Will Lose Reserve Currency Status on Debt Ceiling Standoff

Rio Tinto Warns of Risks for Paying High Premiums for Lithium Mines after Plunging Lithium Prices Triggered Acquisition Rush

Goldman Sachs Lowers Price Forecast for Aluminium, Copper in 2023, Sees Nickel Price Plunging

'Bond King' Jeffrey Gundlach Says Sharp Fed Rate Cuts By Year-End Will Push Up Gold Prices

Zinc Prices to Plunge by 2025, Here's Why

World Bank: Global Commodity Prices to Plunge Precipitously This Year at Fastest Speed since Covid Outbreak

Citigroup Warns European Commercial Real Estate Values Will Plummet 40%, But Sees Medium-Term Opportunity

BofA Sharply Lowers Forecast for Oil Price, Global Oil Consumption in 2023

UBS Raises China GDP Growth Forecast, Sees Earnings from China Stock Market Soaring, RMB Appreciating

Sharp Output Cuts Led to Lithium Ore Shortages, High Import Prices Drove Lithium Salt Producers to Shut Down

US Treasury Bill Rates Soar to Record High on Debt Ceiling Jitters

USGS Rejects Copper as Critical Mineral despite Huge Shortage and Biggest Producers Push, Citing Misleading Arguments

SMM Daily Comments (May 16): Most Base Metals Prices Closed with Losses, SHFE Nickel, Stainless Steel Plunge, Oil Gained on G7 New Measures, US Strategic Petroleum Reserve Replenishment and Supply Concerns

SMM Daily Comments (May 19): LME Metals Rose across the Board, All Ferrous Metals Dropped with Coking Coal Plunging


Pernyataan Sumber Data: Kecuali informasi yang tersedia untuk publik, semua data lainnya diproses oleh SMM berdasarkan informasi publik, komunikasi pasar, dan mengandalkan model database internal SMM. Hanya untuk referensi dan tidak menjadi rekomendasi pengambilan keputusan.

Untuk pertanyaan atau informasi lebih lanjut, silakan hubungi: lemonzhao@smm.cn
Untuk informasi lebih lanjut tentang cara mengakses laporan penelitian kami, hubungi:service.en@smm.cn
Berita Terkait
[Solid-State Battery: EcoPro BM Builds an All-Solid-State Battery Team Covering the Full Chain of “Raw Materials-Materials-Battery Cells,” Targeting Commercialization by 2027]
1 menit yang lalu
[Solid-State Battery: EcoPro BM Builds an All-Solid-State Battery Team Covering the Full Chain of “Raw Materials-Materials-Battery Cells,” Targeting Commercialization by 2027]
Baca Selengkapnya
[Solid-State Battery: EcoPro BM Builds an All-Solid-State Battery Team Covering the Full Chain of “Raw Materials-Materials-Battery Cells,” Targeting Commercialization by 2027]
[Solid-State Battery: EcoPro BM Builds an All-Solid-State Battery Team Covering the Full Chain of “Raw Materials-Materials-Battery Cells,” Targeting Commercialization by 2027]
[Solid-State Battery: EcoPro BM Forms All-Solid-State Battery Team Covering the Full "Raw Material-Material-Battery Cell" Chain, Targeting Commercialization by 2027] On August 26, 2026, EcoPro BM held a kick-off meeting in Gyeonggi Province, officially forming an "all-solid-state battery team" covering the full "raw material-material-battery cell" chain. The project is led by South Korea's Ministry of Trade, Industry and Energy, and EcoPro BM was selected in early August, along with four other enterprises, as a third-phase "super subcontractor" company. Team participants include the Korea Electronics Technology Institute (KETI), the Korea Institute of Science and Technology (KIST), Pohang University of Science and Technology (POSTECH), Hanyang University, and others. EcoPro BM plans to develop sulphide-based solid electrolytes based on high-purity lithium sulphide, with the goal of commercializing sulphide-based all-solid-state batteries by 2027. Reported by Yonhap News Agency and other South Korean media on August 31.
1 menit yang lalu
[SMM Analysis] Permintaan nikel-menengah Tiongkok diperkirakan akan menurun, harga prekursor turun
26 menit yang lalu
[SMM Analysis] Permintaan nikel-menengah Tiongkok diperkirakan akan menurun, harga prekursor turun
Baca Selengkapnya
[SMM Analysis] Permintaan nikel-menengah Tiongkok diperkirakan akan menurun, harga prekursor turun
[SMM Analysis] Permintaan nikel-menengah Tiongkok diperkirakan akan menurun, harga prekursor turun
26 menit yang lalu
Hak Kobalt Voisey's Bay Ecora Naik 90% YoY pada Semester I seiring Ramp-Up Tambang Bawah Tanah Mendekati Penyelesaian
3 jam yang lalu
Hak Kobalt Voisey's Bay Ecora Naik 90% YoY pada Semester I seiring Ramp-Up Tambang Bawah Tanah Mendekati Penyelesaian
Baca Selengkapnya
Hak Kobalt Voisey's Bay Ecora Naik 90% YoY pada Semester I seiring Ramp-Up Tambang Bawah Tanah Mendekati Penyelesaian
Hak Kobalt Voisey's Bay Ecora Naik 90% YoY pada Semester I seiring Ramp-Up Tambang Bawah Tanah Mendekati Penyelesaian
Menurut hasil interim Ecora Royalties 2026 yang dirilis pada 2 September, perusahaan menerima 266 ton kobalt melalui aliran kobalt Voisey's Bay pada paruh pertama tahun ini, naik sekitar 90% dari 140 ton pada periode yang sama tahun 2025. Ecora menyatakan bahwa peningkatan operasi penambangan bawah tanah di Voisey's Bay kini hampir selesai. Didorong oleh volume kobalt yang lebih tinggi dan harga yang lebih kuat, kontribusi portofolio proyek setelah biaya aliran naik menjadi US$13,5 juta pada paruh pertama, naik 230% dari tahun ke tahun, sementara harga rata-rata kobalt yang direalisasikan meningkat menjadi US$28,4/lb dari US$16,5/lb setahun sebelumnya. Sementara itu, Vale Base Metals sedang mengkaji perluasan kapasitas pemrosesan konsentrator Voisey's Bay dari sekitar 2,8 juta ton per tahun menjadi 3,8 juta ton per tahun. Studi pra-kelayakan terkait masih berlangsung, dengan keputusan investasi akhir ditargetkan sekitar tahun 2028. Proyek ini juga merencanakan pengeboran bawah tanah dan permukaan pada tahun 2026 untuk mengoptimalkan rencana tambang, mendukung perluasan sumber daya, dan berpotensi memperpanjang umur tambang. Ecora juga menyatakan bahwa pemeliharaan terjadwal dijadwalkan di konsentrator Voisey's Bay pada kuartal ketiga dan di kilang Long Harbour pada kuartal keempat.
3 jam yang lalu