An estimated daily output of 10,000 mt of molten iron is set to be affected by maintenance for a 4747m³ blast furnace at Anyang Iron & Steel from March 6

SHANGHAI, Mar 5 (SMM) – An estimated daily output of 10,000 mt of molten iron is set to be affected by maintenance for a 4747m³ blast furnace at Anyang Iron & Steel from March 6. 


The maintenance is scheduled to last for four days, according to sources.


Anyang Iron & Steel also planned to conduct maintenance on its 1780mm hot continuous rolling mill for five days from March 4 and a 3500mm Steckel mill for 15 days from March 6. This is expected to affect the daily production of hot-rolled coil (HRC) by 11,000 mt and daily output of moderate-thickness steel plate by 3,800 mt.

 

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Maintenance at Anyang Iron & Steel to affect molten iron, HRC and steel plate production in March - Shanghai Metals Market (SMM)