Home / Metal News / Crude steel production to halt at Jiangxi Pinggang

Crude steel production to halt at Jiangxi Pinggang

iconAug 10, 2018 16:48
Source:SMM
Following suspensions of blast furnaces on Aug 12, some 17,000 mt of total daily production of rebar and wire rod will be affected

SHANGHAI, Aug 10 (SMM) – Jiangxi Pinggang Industrials Holdings in Jiangxi province will suspend a blast furnace of 450m³ and another of 1080m³ on Sunday August 12. Following this, all seven operating blast furnaces owned by the company will cease to be in production. 

The plant’s total daily production of crude steel, estimated at 17,000 mt, will be affected. 

As of Monday August 6, five blast furnaces have been in hot idling mode as the provincial environmental bureau visited the city. 

It remains unclear when the restriction would be lifted, SMM learned. 

Market commentary
Rebar
Wire rods
Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market exchanges, and relying on SMM's internal database model, for reference only and do not constitute decision-making recommendations.

For queries, please contact Lemon Zhao at lemonzhao@smm.cn

For more information on how to access our research reports, please email service.en@smm.cn

Related news