Tangshan Guofeng suspends after failing to meet emission standard

Published: Jul 6, 2018 14:33
One of the two 230m³ sintering machines at Guofeng Iron and Steel in Tangshan was required to suspend during 0:00-24:00 China Standard Time (CST).

SHANGHAI, Jul 6 (SMM) – One of the two 230m³ sintering machines at Guofeng Iron and Steel in Tangshan, Hebei province was required to suspend during 0:00-24:00 China Standard Time (CST) on Friday July 6, on orders from the municipal environmental protection bureau.

At one point on July 4, carbon monoxide emissions at the 230m³ sintering machine exceeded the 6,000mg/m³ threshold that the Tangshan government set on June 15.

Guofeng Iron and Steel has six sintering machines, with two for each of the specifications of 230m³, 132m³, and 110m³.

Plants that failed to meet discharge standards will face a 24-hour suspension of its sintering machines, SMM learned. 

Tangshan steel mills have faced frequent cuts since late May as the city tries to counter heavy air pollution. 

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn