SMM surveys major producers in China’s base metal market every month to get first-hand production data, and the following table shows latest output data for July 2017.

SHANGHAI, Aug. 9 (SMM) – SMM surveys major producers in China’s base metal market every month to get first-hand production data, and the following table shows latest output data for July 2017.

 

Jul. (Preliminary Data)

YoY

Jan.- Jul.

 

YoY

Jun.

(Final Data)

Aug. (E)

Copper cathode

633

-4.67%

4465.5

-0.12%

654

661.5

Alumina

5774

14.4%

39443

20.2%

5661

5814

Aluminum

3120

16.5%

21416

20.9%

3091

3075

Primary lead

251.8

11.27%

1642.6

-6.64%

231.9

249.5

Refined zinc

455

1.62%

3051

-1.73%

462.5*

459.5

Refined nickel

13.8

-3.8%

89.7

-12.4%

12.6

14.3

NPI

35.2

4.45%

224

2.37%

31.6

37.4

Refined tin

14.2

-2.1%

103

6.7%

15.5

14.5

Source: SMM

Unit: 1,000 tonne

Notes: 1. Data in final column (marked with an asterisk) has been revised. 2. NPI output refers to output in Ni content.

Copper

China Copper Cathode Output Falls in July, and to Rise in August, SMM Report

Aluminum

China Aluminum Output to Drop MoM in August as Cuts Outpace New Capacity, SMM Expects

SMM Data: China Alumina Output Surges in July and to Continue Growing in August

Zinc

China Refined Zinc Output Falls in July, but to Grow in August, SMM Says

Lead

China Primary Lead Output to Inch down in August after Rising in July, SMM Reports

Tin

China Tin Output Falls Sharply in July, but to Increase in August, SMM Says

Nickel

China Refined Nickel Output to Grow in August, SMM Predicts

China NPI Output Grows with Rising NPI Price, SMM Reports

For news cooperation, please contact us by email: sallyzhang@smm.cn or service.en@smm.cn.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Shaanxi-Henan UHV DC Project, Final in "Three Exchanges Nine Direct," to Be Completed by 2028
2 hours ago
Shaanxi-Henan UHV DC Project, Final in "Three Exchanges Nine Direct," to Be Completed by 2028
Read More
Shaanxi-Henan UHV DC Project, Final in "Three Exchanges Nine Direct," to Be Completed by 2028
Shaanxi-Henan UHV DC Project, Final in "Three Exchanges Nine Direct," to Be Completed by 2028
On March 31, the National Grid announced that the Shaanxi-Henan ± 800 kV UHV DC project, the final project of the "three exchanges and nine direct" projects in the National "14th Five-Year" plan, with a total investment of 19 billion yuan.It starts in Yulin, Shaanxi, and ends in Kaifeng, Henan, passing through Shaanxi, Shanxi, and Henan provinces. The total length of the line is 728 kilometers, the transmission capacity is 8 million kilowatts, and it is planned to be completed and put into operation in 2028.
2 hours ago
National Grid's Panxi UHV AC Project, a $23.2B Investment, to Span 994km and Complete by 2028
2 hours ago
National Grid's Panxi UHV AC Project, a $23.2B Investment, to Span 994km and Complete by 2028
Read More
National Grid's Panxi UHV AC Project, a $23.2B Investment, to Span 994km and Complete by 2028
National Grid's Panxi UHV AC Project, a $23.2B Investment, to Span 994km and Complete by 2028
On March 31, the National Grid announced that the Panxi UHV AC project, the first UHV AC project to start construction during the "14th Five-Year Plan" of the National Grid, has a total investment of about 23.2 billion yuan. The project will pass through 12 counties (districts) in Liangshan, Yibin, and Leshan, build two 1000 kV substations in Panxi and Chuannan, and expand Tianfu South Station. The total length of the line is 994 kilometers, and it is expected to be completed and put into operation in 2028.
2 hours ago
"Fluctuating Copper Prices and Tight Supply Squeeze Secondary Copper Industry, Pressuring Upstream and Downstream"
21 hours ago
"Fluctuating Copper Prices and Tight Supply Squeeze Secondary Copper Industry, Pressuring Upstream and Downstream"
Read More
"Fluctuating Copper Prices and Tight Supply Squeeze Secondary Copper Industry, Pressuring Upstream and Downstream"
"Fluctuating Copper Prices and Tight Supply Squeeze Secondary Copper Industry, Pressuring Upstream and Downstream"
This week, against the backdrop of fluctuating upward copper prices, the secondary copper industry chain showed a complex situation in which extremely tight upstream raw material supply coexisted with persistent negative margins for downstream finished products. In the secondary copper rod market, SMM data showed that the operating rate fell further to 5.45% this week, down 0.38 percentage points MoM and 25.43 percentage points YoY
21 hours ago