800 million yuan!The largest grid-side independent energy storage project with a single installed capacity!

게시됨: Mar 12, 2024 19:31 (GMT+8)
On the morning of March 11, the 200MW/400MWh grid-side energy storage project in Wuyi County, Jinhua City, Zhejiang Province officially started, which is also the largest grid-side independent energy storage project in Zhejiang Province, which is currently the largest grid-side independent energy storage project in Zhejiang Province, which was signed by Wuyi County, Jinhua City and Sunwoda Smart Energy, with a total planned investment of 800 million yuan. According to Shenzhen Sunwoda Smart Energy Co., Ltd. (hereinafter referred to as Sunwoda Smart Energy), on the morning of March 11, the 200MW/400MWh grid-side energy storage project in Wuyi County, Jinhua City, Zhejiang Province officially started, which is also the largest grid-side independent energy storage project in Zhejiang Province. The project was signed by Wuyi County, Jinhua City, Zhejiang Province and Sunwoda Smart Energy, with a planned total investment of 800 million yuan, and the project will be connected to the grid before June 30, 2024 according to the construction target.

On the morning of March 11, the 200MW/400MWh grid-side energy storage project in Wuyi County, Jinhua City, Zhejiang Province officially started, which is also the largest grid-side independent energy storage project in Zhejiang Province, which is currently the largest grid-side independent energy storage project in Zhejiang Province, which was signed by Wuyi County, Jinhua City and Sunwoda Smart Energy, with a total planned investment of 800 million yuan.
According to Shenzhen Sunwoda Smart Energy Co., Ltd. (hereinafter referred to as Sunwoda Smart Energy), on the morning of March 11, the 200MW/400MWh grid-side energy storage project in Wuyi County, Jinhua City, Zhejiang Province officially started, which is also the largest grid-side independent energy storage project in Zhejiang Province. The project was signed by Wuyi County, Jinhua City, Zhejiang Province and Sunwoda Smart Energy, with a planned total investment of 800 million yuan, and the project will be connected to the grid before June 30, 2024 according to the construction target.

Meng Xiangjun, general manager of Sunwoda Smart Energy, said at the groundbreaking ceremony: "Sunwoda (300207) actively responds to the national 'dual carbon' strategy, based on its own lithium battery manufacturing advantages, and focuses on the promotion of multiple types of energy storage application scenarios. The Wuyi project is the beginning of Sunwoda's strategic layout of energy storage on the grid side of Zhejiang Province, and it is also a benchmark demonstration project of energy storage for the group."

According to the data, on August 31, 2023, the Zhejiang Provincial Energy Bureau issued the "Notice on Issuing the New Energy Storage Installed Target Tasks before the Peak Summer of 2024", and the Jinhua Wuyi 200MW/400MWh grid-side energy storage project was included in the Provincial Energy Bureau's new new energy storage task plan before the peak summer of 2024, and the document clearly states that "the projects included in the list of projects in this notice are regarded as included in the 14th Five-Year Development Plan for New Energy in Zhejiang Province". At the same time, the project has been included in the 2024 major construction projects of Zhejiang Province to expand effective investment in the "thousands of trillions" project.

It is understood that after the completion of the project, it can accept power grid dispatching, effectively alleviate the intermittent and random impact of wind energy, photovoltaic and other energy sources on the power grid, and has significant advantages in peak regulation, frequency regulation, phase modulation and emergency backup, etc., which is of great significance for promoting green energy transformation, responding to extreme events, ensuring energy security, promoting high-quality energy development, and achieving the "double carbon" goal.

데이터 출처 설명: 공개 정보를 제외한 모든 데이터는 SMM이 공개 정보, 시장 커뮤니케이션 및 SMM 내부 데이터베이스 모델을 기반으로 가공한 것입니다. 본 자료는 참고용이며 의사결정 권고를 구성하지 않습니다.

문의 사항이 있거나 자세한 정보를 원하시면 아래로 연락해 주시기 바랍니다: lemonzhao@smm.cn
리서치 보고서 열람 방법에 대한 자세한 내용은 아래로 문의하시기 바랍니다:service.en@smm.cn
관련 뉴스
[SMM 분석] 하류 재고 확보로 리튬헥사플루오로포스페이트 수요 증가, 공급 증가 속도는 여전히 더딤
3시간 전
[SMM 분석] 하류 재고 확보로 리튬헥사플루오로포스페이트 수요 증가, 공급 증가 속도는 여전히 더딤
더 보기
[SMM 분석] 하류 재고 확보로 리튬헥사플루오로포스페이트 수요 증가, 공급 증가 속도는 여전히 더딤
[SMM 분석] 하류 재고 확보로 리튬헥사플루오로포스페이트 수요 증가, 공급 증가 속도는 여전히 더딤
[SMM 분석: 하류 재고 확보로 LiPF6 수요 증가, 공급 증가 속도는 여전히 더딤] 2026년 9월 중국 LiPF6 생산량은 소폭 증가세를 이어가며 전월 대비 약 3.4%, 전년 동기 대비 약 59% 증가했다. 전반적인 공급 확대 속도는 여전히 더디며, 타이트한 수급 균형이 지속됐다.
3시간 전
[SMM 분석] 9월 수요 증가 기대에 못 미쳐, 전해액 생산 증가폭 둔화
5시간 전
[SMM 분석] 9월 수요 증가 기대에 못 미쳐, 전해액 생산 증가폭 둔화
더 보기
[SMM 분석] 9월 수요 증가 기대에 못 미쳐, 전해액 생산 증가폭 둔화
[SMM 분석] 9월 수요 증가 기대에 못 미쳐, 전해액 생산 증가폭 둔화
[SMM 분석: 9월 수요 증가 기대치 하회, 전해액 생산 증가폭 축소] 2026년 9월, 중국 전해액 산업의 공급과 수요가 동시에 확대되고 시장 심리가 지속적으로 개선되었음에도 불구하고, 증가율은 전월 대비 뚜렷하게 축소되었다. SMM 데이터에 따르면, 9월 중국 전해액 총생산량은 8월 대비 약 2.8% 증가했으며, 전년 동기 대비 약 66% 증가했다.
5시간 전
[에너지 저장: LONGi, 쑤저우 기지 생산 개시, 그리드 규모 통합 용량 50GWh 목표]
2026년 10월 10일 19:47 (GMT+8)
[에너지 저장: LONGi, 쑤저우 기지 생산 개시, 그리드 규모 통합 용량 50GWh 목표]
더 보기
[에너지 저장: LONGi, 쑤저우 기지 생산 개시, 그리드 규모 통합 용량 50GWh 목표]
[에너지 저장: LONGi, 쑤저우 기지 생산 개시, 그리드 규모 통합 용량 50GWh 목표]
론지의 쑤저우 기지가 10월 9일 공식 가동을 시작했으며, 컨테이너형 스토리지, C&I 스토리지, 제어 캐비닛을 포괄한다. 그리드 규모 통합 라인은 10월부터 연간 31GWh 생산능력을 갖추고, 2027년에는 50GWh로 확대되며, 10월 말까지 연간 1만 대 이상의 C&I 유닛을 생산할 예정이다. 론지는 2025년 11월 징코에너지의 경영권(의결권 약 62%)을 인수했으며, 2026년 상반기 누적 스토리지 수주량은 3GWh를 초과했고, 연간 출하 목표는 6GWh이다.
2026년 10월 10일 19:47 (GMT+8)
800 million yuan!The largest grid-side independent energy storage project with a single installed capacity! - Shanghai Metals Market (SMM)