AES's 200MW/800MWh energy storage project was approved in the United States.

게시됨: Jan 31, 2024 18:16
출처: SMM
The Indiana Utility Regulatory Commission (IURC) has approved a proposed large-scale battery storage project developed by AES Corporation's regional utility subsidiary in the US.

The Indiana Utility Regulatory Commission (IURC) has approved a proposed large-scale battery storage project developed by AES Corporation's regional utility subsidiary in the US.

AES Indiana said late last week (January 26) that the regulator had approved the 200MW/800MWh battery storage project in Pike County, Indiana. The standalone Battery Energy Storage System (BESS) asset is expected to come online in December of this year.

The asset is being constructed at the site of AES' Petersburg Generating Station coal-fired power plant in Indiana and the last coal-fired power plant in its portfolio. The coal-fired units at the 2,146MW plant will be shut down by 2025 as parent company AES has committed to exiting coal, and AES has proposed to convert the facility to natural gas, in addition to developing hundreds of megawatts of wind, solar photovoltaic and batteries in the region.

The project would connect to the Mid-Continent Independent System Operator (MISO) grid and the ISO's wholesale market. AES Indiana, formerly known as Indianapolis Power & Light (IPL), which has about 500,000 customers in Indianapolis and central Indiana, said it will bring MISO online in the 2024-2025 winter season, when demand typically peaks. The utility issued a request for proposals (RFP) in February 2022 that calls for system delivery to be accomplished on a turnkey basis, i.e., not a power purchase agreement (PPA) or other third-party contract. BESS will be connected to the AES Indiana transmission line via a new substation.

Midwestern U.S. Has Underlying Drivers for Strong BESS Demand

In AES Indiana's recently filed 2022 Integrated Resource Plan (IRP), the company identified an additional 1,300 MW of wind, solar PV and battery storage in its resource portfolio by 2027.

The utility has been criticized for choosing to partially replace coal generating capacity with natural gas, but believes that a mix of renewables and natural gas will be the best combination to maintain supply reliability year-round and meet growing peak demand. In general, MISO and the Midwest have traditionally relied heavily on coal for power generation.

Michigan recently adopted a state energy storage deployment goal of 2,500 megawatts (MW) by 2030, becoming the first Midwestern state to adopt a 100 percent clean energy standard by 2040. Michigan has set the pace for the Midwest's energy transition as clean energy legislation passed late last year.

The Midwest's need for energy capacity to make up for supply shortfalls as coal plants are retired and demand increases with electrification means the Midwest has the fundamental drivers to become one of the largest battery storage markets in the United States. In late 2022, MISO added energy storage to its wholesale market portfolio, adopting the definition of an energy storage resource (ESR) used by the Federal Energy Regulatory Commission (FERC).

MISO modeled its portfolio with four hours of lithium-ion battery storage, leading developers to propose BESS projects of that duration, such as AES Indiana's Pike County project.

For more information, please contact: cathycai@smm.cn

데이터 출처 설명: 공개 정보를 제외한 모든 데이터는 SMM이 공개 정보, 시장 커뮤니케이션 및 SMM 내부 데이터베이스 모델을 기반으로 가공한 것입니다. 본 자료는 참고용이며 의사결정 권고를 구성하지 않습니다.

문의 사항이 있거나 자세한 정보를 원하시면 아래로 연락해 주시기 바랍니다: lemonzhao@smm.cn
리서치 보고서 열람 방법에 대한 자세한 내용은 아래로 문의하시기 바랍니다:service.en@smm.cn
관련 뉴스
세계 최고 고도 660MW 초초임계 화력발전소의 고비율 고알칼리탄 혼소
2026년 9월 2일 10:35
세계 최고 고도 660MW 초초임계 화력발전소의 고비율 고알칼리탄 혼소
더 보기
세계 최고 고도 660MW 초초임계 화력발전소의 고비율 고알칼리탄 혼소
세계 최고 고도 660MW 초초임계 화력발전소의 고비율 고알칼리탄 혼소
8월 25일 18시, 국가전력투자그룹 칭하이성투자 3×660MW '소형기 대형기 교체' 화력발전 프로젝트 3호기가 168시간 전부하 시운전을 성공적으로 통과하여, 세계 최고 고도 660MW 초초임계 고비율 고알칼리탄 혼소 화력발전소의 전 용량 가동을 실현했다. 프로젝트가 전 용량 가동에 도달한 후, 총 설비 용량은 1980MW에 달하며, 연평균 안정적인 발전량은 80억 kWh 이상으로 칭하이성 전체의 전력 수요를 완전히 충족할 수 있다.
2026년 9월 2일 10:35
중국남방전력망에너지, 태양광 기업 2곳 지분 100% 양도 예정
2026년 9월 2일 10:35
중국남방전력망에너지, 태양광 기업 2곳 지분 100% 양도 예정
더 보기
중국남방전력망에너지, 태양광 기업 2곳 지분 100% 양도 예정
중국남방전력망에너지, 태양광 기업 2곳 지분 100% 양도 예정
8월 26일, 베이징 공공자원 거래 서비스 센터는 국유 지분 상장 양도 공고 두 건을 발표했다. 차이나 서던 파워 그리드 종합 에너지 유한공사(차이나 서던 파워 그리드 에너지)는 소유하고 있는 두 태양광 프로젝트 회사의 지분 100%를 양도할 계획이다. 이번 양도 대상은 두 개의 전액 출자 태양광 기업인 난뎬(청마이) 신에너지 기술 유한공사와 스쭝 상푸 이허 태양광 투자 유한공사이다.
2026년 9월 2일 10:35
인도, 상반기 태양광 27GW 신규 설치로 사상 최대 기록
2026년 9월 2일 10:32
인도, 상반기 태양광 27GW 신규 설치로 사상 최대 기록
더 보기
인도, 상반기 태양광 27GW 신규 설치로 사상 최대 기록
인도, 상반기 태양광 27GW 신규 설치로 사상 최대 기록
메르콤 인디아 리서치가 발표한 ‘인도 태양광 시장 업데이트 2026년 2분기 및 상반기’ 보고서에 따르면, 인도는 2026년 상반기에 27GW의 태양광 발전 용량을 추가하며 2025년 상반기 18GW 대비 전년 동기 50% 증가해 신기록을 세웠다. 이 기간 추가된 전체 발전 용량 36GW 중 태양광이 76%를 차지했다.
2026년 9월 2일 10:32
AES's 200MW/800MWh energy storage project was approved in the United States. - Shanghai Metals Market (SMM)