On December 4th, the last set of tower barrels for the 480-megawatt Wuxing Wind Power Project (West Zone) of China General Nuclear Power Corporation's Yunnan Branch was dispatched from the Shilin base, marking the completion of the production and delivery of all 38 sets of tower barrels for the project.
The Wuxing Wind Power Project, located in the eastern and northeastern mountain ridges of Xuanwei City, Qujing City, Yunnan Province, consists of three zones: south, west, and north. The west zone utilizes the Shanghai Electric 5.6-202-120 six-section model, with a maximum diameter of 5.3 meters for the tower barrel flange. Each set of tower barrels has a total weight of approximately 401 tons, with a total project volume of 15,238 tons.