On November 25th, in Datong Town, Tianchang City, Anhui Province, electric power technicians conducted pre-commissioning acceptance checks on the electrical equipment in the 220 kV Youhao Smart Substation. On that day, the Anhui Power Grid's key project for peak-load regulation and winter power supply, the Tianchang City 220 kV Youhao Transmission and Substation Project, with a total investment of 275 million yuan, was officially put into operation, making it the 160th substation with a voltage level of 35 kV and above completed and put into operation in the Chuzhou Power Grid.
After the project is put into operation, the additional power supply capacity will be 360,000 kilowatts, providing strong energy security for the local economic and social development. It will meet the power supply demand for the construction of the Anhui Tianchang section of the new Nanjing-Huai'an intercity railway, ensuring reliable electricity supply for urban and rural residents and agricultural production. At the same time, as a key guarantee project for the construction of the new energy base in the eastern part of Chuzhou, the project will provide a fast grid connection for the abundant development of new energy (wind, photovoltaic, energy storage) in the Tianchang area.
![Los precios del magnesio suben por tercera sesión consecutiva: el lado de los costos sigue "ardiendo" mientras la demanda lucha por tomar el relevo [Comentario de SMM]](https://imgqn.smm.cn/usercenter/EutUV20251217171724.jpeg)