Phase 1 of Collie large-scale energy storage project in Western Australia connected to grid

Publicado: Jul 17, 2024 20:37 (GMT+8)
Fonte: SMM
Neoen connects 219MW/877MWh first phase of Collie battery project in Western Australia. 90% of its capacity has already been booked by AEMO. SMM believes that...

On Monday, French renewable energy company Neoen SA announced the grid-connection of the first phase of its Collie large-scale battery energy storage project in Greater Western Australia.

The Collie Phase I is sized at 219MW/877MWh. as part of the 1GW/4GWh Collie energy storage project, which was launched by Neoen in 2021. According to an earlier report by SMM, the commissioning of the first phase was scheduled to officially start commercial operation in October this year, and it is expected that it will be successfully commissioned on time.

Neoen had already competitively tendered for a capacity service delivery contract at the project last year with the Australian Energy Market Operator (AEMO), providing AEMO with 90% (approximately 197MW) of the Collie Phase 1 project's four-hour capacity. The project utilises Tesla's Megapack 2XL all-in-one energy storage product, which is one of the larger scale uses of the product today.

The second phase of the Collie Battery is 341MW/1,363MWh in size and will consist of 348 Tesla Megapack 2 XLs. It will operate under a four-hour capacity service contract signed with AEMO in April this year.

Declaração sobre a Fonte de Dados: Com exceção das informações publicamente disponíveis, todos os demais dados são processados pela SMM com base em informações publicamente disponíveis, comunicação de mercado e com base no modelo de base de dados interna da SMM. São apenas para referência e não constituem recomendações para a tomada de decisão.

Para quaisquer perguntas ou para obter mais informações, entre em contato: lemonzhao@smm.cn
Para mais informações sobre como aceder aos nossos relatórios de investigação, entre em contato:service.en@smm.cn
Notícias Relacionadas
[Armazenamento de energia: Sungrow e CATL estão entre os cinco vencedores da licitação de armazenamento de 2,98 GWh da CNNC]
16 Oct 2026 14:03 (GMT+8)
[Armazenamento de energia: Sungrow e CATL estão entre os cinco vencedores da licitação de armazenamento de 2,98 GWh da CNNC]
Leia mais
[Armazenamento de energia: Sungrow e CATL estão entre os cinco vencedores da licitação de armazenamento de 2,98 GWh da CNNC]
[Armazenamento de energia: Sungrow e CATL estão entre os cinco vencedores da licitação de armazenamento de 2,98 GWh da CNNC]
A CNNC anunciou os vencedores de sua licitação centralizada de sistemas de armazenamento de energia LFP para 2026-2028 em 14 de outubro. Sungrow, CATL, Zhongtian Energy Storage, CRRC Zhuzhou Institute e Kehua venceram com propostas de RMB 0,4995-0,5329/Wh. A licitação de 2,98 GWh atraiu 33 proponentes, abrangendo sistemas de 2 horas e 4 horas com projeto de 1500 V CC e requisitos para serviços de rede, como regulação primária de frequência e suporte de potência reativa.
16 Oct 2026 14:03 (GMT+8)
[Armazenamento de energia: embarques acumulados da HiTHIUM ultrapassam 200 GWh, linha de longa duração em Chongqing apoia entregas]
16 Oct 2026 14:03 (GMT+8)
[Armazenamento de energia: embarques acumulados da HiTHIUM ultrapassam 200 GWh, linha de longa duração em Chongqing apoia entregas]
Leia mais
[Armazenamento de energia: embarques acumulados da HiTHIUM ultrapassam 200 GWh, linha de longa duração em Chongqing apoia entregas]
[Armazenamento de energia: embarques acumulados da HiTHIUM ultrapassam 200 GWh, linha de longa duração em Chongqing apoia entregas]
A HiTHIUM realizou uma cerimônia de marco de 200 GWh embarcados em Chongqing no dia 15 de outubro, dobrando a partir de 100 GWh em pouco mais de um ano e subindo para o 2º lugar global em 2025, ante o quinto em 2023. Sua fábrica em Chongqing opera a primeira linha dedicada do mundo para células de armazenamento de longa duração, produzindo células da classe de 200 kAh por hora com mais de 89% de automação, e foi nomeada Fábrica Farol do Fórum Econômico Mundial em janeiro. Desde que se instalou em Tongliang, a empresa atraiu 18 empresas a montante e a jusante, gerando RMB 10,85 bilhões em produção de janeiro a setembro, um aumento de 54% em relação ao ano anterior.
16 Oct 2026 14:03 (GMT+8)
[Armazenamento de energia: LONGi inicia produção na base de Suzhou, capacidade de integração em escala de rede visada em 50 GWh]
10 Oct 2026 19:47 (GMT+8)
[Armazenamento de energia: LONGi inicia produção na base de Suzhou, capacidade de integração em escala de rede visada em 50 GWh]
Leia mais
[Armazenamento de energia: LONGi inicia produção na base de Suzhou, capacidade de integração em escala de rede visada em 50 GWh]
[Armazenamento de energia: LONGi inicia produção na base de Suzhou, capacidade de integração em escala de rede visada em 50 GWh]
A base da LONGi em Suzhou iniciou oficialmente a produção em 9 de outubro, abrangendo armazenamento em contêineres, armazenamento C&I e gabinetes de controle. Sua linha de integração em escala de rede terá capacidade anualizada de 31 GWh a partir de outubro, expandindo para 50 GWh em 2027, além de mais de 10.000 unidades C&I por ano até o final de outubro. A LONGi adquiriu o controle da Jingko Energy (cerca de 62% dos direitos de voto) em novembro de 2025; os pedidos acumulados de armazenamento ultrapassaram 3 GWh no primeiro semestre de 2026, com meta de embarque de 6 GWh para o ano completo.
10 Oct 2026 19:47 (GMT+8)