On September 30, Huadian Liaoning Energy Development Co., Ltd. announced the bid evaluation results for the PC contract of the Huadian Tiaobingshan 450,000 kW Wind Power Hydrogen Production Coupling Green Methanol Integrated Demonstration Project in Liaoning. China Huadian Engineering Co., Ltd. and PowerChina Nuclear Engineering Co., Ltd. were ranked as the first and second preferred bidders, respectively.
Announcement Details:
First Preferred Bidder: China Huadian Engineering Co., Ltd., with a bid price of 3,291.968566 million yuan;
Second Preferred Bidder: PowerChina Nuclear Engineering Co., Ltd., with a bid price of 3,298.102654 million yuan.
This PC contract project is located in Tiaobingshan City, Tieling, Liaoning Province, and is a key component of the Huadian Tiaobingshan 450,000 kW Wind Power Hydrogen Production Coupling Green Methanol Integrated Demonstration Project. The project's construction covers the entire chain from energy supply to hydrogen production and methanol synthesis, specifically including: a 450 MW wind farm, power transmission lines and step-down substations, grid connection systems, water electrolysis hydrogen production and hydrogen filling areas, a 100,000 t/a methanol synthesis and distillation unit, a 150,000 t/a carbon dioxide compression and purification unit, as well as supporting facilities such as a comprehensive building, central laboratory, central control room, hydrogen storage and loading/unloading facilities, and utilities for water, electricity, and gas.
Project Performance Period: From September 28, 2025, to June 20, 2027.
Tender Scope: This PC contract (No. CHDTDZ059/19-ZB-01201) encompasses all work for the wind power section (excluding wind turbine procurement), chemical section, transmission line section, and grid connection system section, including equipment procurement, installation and commissioning, construction works, land lease coordination, permit acquisition, trial operation and handover, and warranty services, with the goal of achieving the National Quality Engineering Gold Award. Specific details include:
450 MW wind farm;
Step-up substation and energy storage system;
Power transmission lines and step-down substations (from the wind farm to the hydrogen-methanol line, and the 220 kV hydrogen-methanol step-down substation);
Grid connection system (from the grid tie-line to the 66/10 kV backup power line on the chemical side, and the 220 kV tie-line from the hydrogen production step-down substation to the Tiaobingshan substation).
Water electrolysis hydrogen production and hydrogen filling area;
Carbon dioxide compression, purification, and storage (including the pipeline supporting project from the plant area of SDIC Bioenergy (Tieling) Co., Ltd. to the carbon dioxide purification unit);
100,000 t/a methanol synthesis and distillation system;
Supporting facilities such as the comprehensive building, central laboratory, central control room, hydrogen storage and loading/unloading facilities, and utilities for water, electricity, and gas.
This project does not accept consortium bids.
[General Contracting for Construction - PC General Contracting]
Bid Price: 32,919,685.66 million yuan, with both quality and construction period meeting the tender document requirements;
Qualification Certificates: Grade II General Contracting for Power Engineering Construction (No. D211067910, valid until December 6, 2028), Grade II General Contracting for Petrochemical Engineering Construction (No. D211067910, valid until December 6, 2028), Work Safety Permit (No. Jing JZ An Xu Zheng Zi [2020] 222754, valid until October 23, 2026);
Core Performance: Three wind power projects (Heilongjiang Huadian Ning'an Fengshuishan 200 MW Wind Power Project, General Contracting for Yunnan Huadian Honghe Gejiu Houzishan 200 MW Wind Power Project, Construction of Heilongjiang Huadian Harbin Yilan Jiguanshan Phase IV 200 MW Wind Power Project), one hydrogen production project (PC General Contracting for the Hydrogen Production Station of the CNNC Ningdong Clean Energy Hydrogen Production Project);
Project Manager: Xu Lianjiang, Grade I Registered Constructor in Mechanical and Electrical Engineering (Jing 1112011201221679), Senior Engineer, previously presided over the EPC General Contracting for the Coal Conveying Island of Hunan Huadian Pingjiang Phase I 2x1000 MW Coal Power Project, and the Inner Mongolia Huadian Baotou Damaoqi 200,000 kW New Energy Hydrogen Production Demonstration Project;
Safety Director: Ye Xiang, National Registered Safety Engineer (10080042953), participated in the EPC General Contracting for Hubei Huadian Honghu Fengkou 44 MW Fishery-Photovoltaic Complementary PV Power Generation Project, and the PC General Contracting for the Hydrogen Production Station of the CNNC Ningdong Clean Energy Hydrogen Production Project.
Bid Price: 32,981,026.54 million yuan, with both quality and construction period meeting the tender document requirements;
Qualification Certificates: Special Grade General Contracting for Power Engineering Construction (No. D137006795, valid until December 22, 2028), Grade II General Contracting for Petrochemical Engineering Construction (No. D237120959, valid until December 26, 2028), Work Safety Permit (No. Lu JZ An Xu Zheng Zi [2005] 180043, valid until March 9, 2026);
Core Performance: One wind power project (General Contracting for Section 1 of Qinghai Mangya Luneng New Energy Mangya Lenghu 500,000 kW Wind Power Project), one hydrogen production project (PC General Contracting for Shandong Huadian Weifang Hydrogen Energy Storage Demonstration Project);
Project Manager: Xia Lian, Grade I Registered Constructor in Mechanical and Electrical Engineering (Lu 1372016201717840), Senior Engineer, presided over the EPC for Shandong Yucheng Weihe Wind Farm 50 MW Wind Power Project, Jingneng Jingyuan Sanfengyuan 50 MW Wind Power Project EPC, etc.;
Safety Director: Li Wenling, National Registered Safety Engineer (37100085877), participated in the newly built Weifang-Yantai Railway Supporting Zhebu 49.8 MW Wind Power Project, and the EPC General Contracting for Jingneng Hua County 100,000 kW Wind Power Project.
If a bidder or other interested party has an objection to the bid evaluation results, it may be raised through the complaint and objection system on the Huadian Group E-Commerce Platform during the publicity period of the successful bid candidates. The procedure is as follows: lower right corner of the platform homepage → login verification → select "Bid Objection" → associate project → select stage → upload supporting documents → maintain contact information.
Company Name: Huadian Liaoning Energy Co., Ltd. Receiving Department: Materials Management Department Contact Number: 024-83995512
If a bidder or other interested party believes that the procurement activities do not comply with laws and regulations, a complaint may be filed within 10 days from the date of awareness through the complaint and objection system on the Huadian Group E-Commerce Platform, following the same procedure as above.
Company Name: Huadian Liaoning Energy Co., Ltd. Receiving Department: Materials Management Department Contact Number: 024-83995512
None
Bid Inviter: Diaobingshan Huadian Clean Energy Co., Ltd. Address: Room 209, Zone 209, Diaobingshan City, Tieling City, Liaoning Province Contact Person: Miao Haixing Phone: 02477700508 Email: miaohaixing@chd.com.cn
Bidding Agency: Huadian Tendering Co., Ltd. Address: No. 2, Xuanwumennei Street, Xicheng District, Beijing Contact Person: Chen Juntian Phone: 010-83565892 Email: chenjuntian@chd.com.cn