Home / Metal News / Green Hydrogen Project Tracking — ChinaCoal's 100,000 mt/year Liquid Sunshine Methanol Project's Hydrogen Production Unit Regains Approval

Green Hydrogen Project Tracking — ChinaCoal's 100,000 mt/year Liquid Sunshine Methanol Project's Hydrogen Production Unit Regains Approval

iconJul 15, 2025 09:20
Source:SMM

Recently, the PV power generation and hydrogen production unit project of the 100,000 mt/year Liquid Sunshine - Carbon Dioxide and Green Hydrogen to Methanol Technology Demonstration Project has been approved for filing.

According to the project information, the project is located in the Tuke Industrial Project Area of the Sulige Economic Development Zone, Wushen Banner, Ordos City. The project unit is ChinaCoal Ordos Energy & Chemical Co., Ltd., with a total investment of 3.0818 billion yuan.

This project involves the construction of a new 400MW (AC side) PV power generation system and a hydrogen production and storage system with a hydrogen supply capacity of 21,000 mt/year. The hydrogen production system has a designed capacity of 46,200Nm³/h, and the hydrogen storage system is equipped with 10 spherical tanks of 2,000m³ each. Additionally, it includes supporting facilities such as step-down stations and public auxiliary engineering facilities. The average annual power generation of the PV power generation unit over 25 years is approximately 728.5779 million kWh. The electricity consumption method for this project is self-generation and self-use, with the surplus being connected to the grid. Most of the electricity generated from the new energy field is supplied to the electrolytic water hydrogen production device for green hydrogen production. No more than 20% of the total new energy power generation is connected to the grid through a 220kV grid connection line, with the grid connection point being the 220kV side of the Tuhudai 220kV Substation.

The originally planned construction period for this project was from July 2023 to July 2025. However, the project has been delayed by one year, and the project unit has promptly reported the construction progress to the online supervision platform.

Project Filing Notification

Project Code: 2303-150626-60-01-424072

Project Unit: ChinaCoal Ordos Energy & Chemical Co., Ltd.

The PV power generation and hydrogen production unit project of the 100,000 mt/year Liquid Sunshine - Carbon Dioxide and Green Hydrogen to Methanol Technology Demonstration Project that you submitted for filing complies with industrial policies and market access standards and is hereby approved for filing. Please proceed with relevant work accordingly. Before commencing construction, other procedures required by laws and regulations must be completed.

Construction Location: Tuke Industrial Project Area of the Sulige Economic Development Zone, Wushen Banner, Ordos City

Total Investment: 3.0818 billion yuan, including 924.534 million yuan of self-owned funds, 0 yuan of bank loans applied for, and 2.157246 billion yuan from other sources.

Planned Construction Period: From July 2023 to July 2025

Construction Scale and Content: This project involves the construction of a new 400MW (AC side) PV power generation system and a hydrogen production and storage system with a hydrogen supply capacity of 21,000 mt/year. The hydrogen production system has a designed capacity of 46,200Nm³/h, and the hydrogen storage system is equipped with 10 spherical tanks of 2,000m³ each. Additionally, it includes supporting facilities such as step-down stations and public auxiliary engineering facilities. The average annual power generation of the PV power generation unit over 25 years is approximately 728.5779 million kWh. The electricity consumption method for this project is self-generation and self-use, with the surplus being connected to the grid. Most of the electricity generated in the new energy field area is supplied to the electrolysis of water for hydrogen production devices to produce green hydrogen. No more than 20% of the total new energy power generation is connected to the grid through a 220kV grid connection line, with the grid connection point being the 220kV side of the Tuhudai 220kV Substation.

Supplementary Explanation: The project has been postponed for one year, and the project unit has promptly reported the construction progress to the online supervision platform.

(Note: If the project fails to commence construction within two years from the date of filing or fails to handle any other procedures, and the project unit decides to continue implementing the project, please provide an explanation through the online platform; if it decides not to continue, please apply for the cancellation of the filed project. If no explanation is provided and the project is not cancelled after the two-year period, the filing authority will delete the filed project and announce it on the online platform.)

Additional Information

: According to the "Application for Filing Explanation Document" submitted by the project unit on July 10, 2025, after verification, the project explanation complies with industrial policies and market access standards, and the filing information is valid, allowing the project to continue with subsequent work.

Wushen Banner Energy Bureau

July 10, 2025

Source: Online Approval Service Hall for Investment Projects in the Inner Mongolia Autonomous Region