Tracking Green Hydrogen Projects - Qinghai Province's First Green Electricity-to-Hydrogen Project Achieves Commercial Delivery

Published: Apr 29, 2025 17:24

On 27 April, as a hydrogen tube trailer loaded with high-purity green hydrogen slowly exited the factory area of the Huadian Delingha PEM Water Electrolysis for Hydrogen Production Demonstration Project, Qinghai Province's first green electricity-to-hydrogen project, the "Huadian Delingha PEM Water Electrolysis for Hydrogen Production Demonstration Project", officially announced the commercial operation and hydrogen delivery. This not only marks a significant breakthrough in China's green hydrogen production technology in high-altitude and cold regions, but also injects strong momentum into the development of the entire hydrogen industry chain on the Qinghai-Tibet Plateau and even in western China as the "first order of plateau green hydrogen", becoming a vivid footnote to the green energy transition under the "dual carbon" goals.

Project Overview

  • Project Name: Huadian Delingha PEM Water Electrolysis for Hydrogen Production Demonstration Project.

  • Project Location: Delingha City, Haixi Prefecture, Qinghai Province.

  • Project Entity: Huadian Qinghai Company.

Project Scale and Investment

  • Hydrogen Production Scale: 600 Nm³/h, with an annual hydrogen production capacity of 153 mt.

  • Total Investment: RMB 150 million.

Project Technology

  • Hydrogen Production Technology: Adopting internationally advanced PEM water electrolysis technology, replacing traditional alkaline electrolyzers with perfluorosulfonic acid proton exchange membranes, offering significant advantages such as high hydrogen purity (99.999%), low energy consumption, and fast response speed.

  • Collaborative Control System: In response to the extreme environmental conditions in Delingha, with an altitude of 3,000 meters, annual average sunshine exceeding 3,000 hours, and a diurnal temperature variation exceeding 30°C, an innovative "PV-hydrogen-storage" collaborative control system was developed, overcoming world-class challenges such as electrolysis efficiency degradation and poor equipment weather resistance in high-altitude regions.

Project Construction and Operation

  • Construction Period: Construction commenced on 3 November 2,022, with official commissioning on 28 September 2,023, completion of a 72-hour continuous trial run on 6 April 2,024, and achievement of commercial operation and hydrogen delivery on 27 April 2,025.

  • Supporting Facilities: Construction of a hydrogen refuelling station with a capacity of 500 kg/day (12 hours), equipped with three sets of megawatt-class PEM water electrolysis and 20 MPa hydrogen filling systems.

Project Significance

  • Energy Transition: Promoting the transition of the energy structure from "fossil fuel-dominated" to "green hydrogen-supported", aiding in the achievement of the "dual carbon" goals.

  • Industrial Development: Injecting strong momentum into the development of the entire hydrogen industry chain on the Qinghai-Tibet Plateau and even in western China, promoting local economic development.

  • Technological Innovation: Resolving the "bottleneck" issues of localisation for key core materials and equipment such as proton exchange membranes and gas diffusion layers, with significant scientific and industrial demonstration significance.

  • Consumption Challenges: Overcoming the dual dilemmas of "difficult green electricity consumption" and "expensive industrial hydrogen use" in north-west China.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.