0.5652~0.5658 yuan/Wh! The bidding for the 1.02 GWh standalone ESS EPC in Hebei has been opened!

Published: Mar 26, 2025 11:22
【0.5652~0.5658 yuan/Wh! Hebei 1.02GWh Standalone ESS EPC Tender Opened!】Polaris ESS News: On March 25, the EPC tender for the Hebei Shangyi 300MW/1200MWh standalone ESS power station (Phase II) expansion project of 210MW/840MWh and 90MW/180MWh was opened. The total tender scale was 300MW/1020MWh, with the bid prices from the three consortiums ranging from 0.5652 to 0.5658 yuan/Wh. Moreover, subsidiaries of China Railway Group participated in all three consortiums.

Polaris Energy Storage News: On March 25, the EPC tender for the 210MW/840MWh and 90MW/180MWh expansion projects of the Hebei Shangyi 300MW/1200MWh standalone ESS power station (Phase II) was opened. The total tender scale was 300MW/1020MWh, with the bid prices of the three consortiums ranging from 0.5652 to 0.5658 yuan/Wh. Moreover, all three consortiums included subsidiaries of China Railway Group.

The first winning candidate was a consortium of Shanghai Electric Power Design Institute Co., Ltd. and China Railway Ninth Bureau Group Electric Engineering Co., Ltd., with a bid price of 576.981 million yuan, equivalent to a unit price of 0.5657 yuan/Wh.

The second winning candidate was a consortium of Sichuan Electric Power Design & Consulting Co., Ltd. and China Railway First Bureau Group Electric Engineering Co., Ltd., with a bid price of 576.4984 million yuan, equivalent to a unit price of 0.5652 yuan/Wh.

The third winning candidate was a consortium of PowerChina Jilin Electric Power Survey & Design Institute Co., Ltd. and China Railway 12th Bureau Group Electrification Engineering Co., Ltd., with a bid price of 577.1658 million yuan, equivalent to a unit price of 0.5658 yuan/Wh.

According to the previous tender, the project is located in Shangyi County, Zhangjiakou City, Hebei Province. This project involves the construction of a new 210MW/840MWh ESS power station in Phase II, while expanding the Phase I 90MW/180MWh ESS power station to 90MW/360MWh. The ESS battery uses LFP batteries, and both the battery system and power conversion system of the ESS station adopt an outdoor container layout scheme.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
15 hours ago
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Read More
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
Beijing Launches 500-kV Power Project in Fengtai, Boosting Grid Resilience and Industrial Growth
On January 28th, the construction of the 500-kilovolt power transmission and transformation project in Fengtai, Beijing officially started. This project is the first newly-built 500-kilovolt power grid project in Beijing during the 15th Five-Year Plan period. It will significantly enhance the resilience and power receiving capacity of the southern Beijing power grid and provide reliable power support for Beijing to continuously optimize the investment structure and vigorously develop high-end, precise, and cutting-edge industries. The 500-kilovolt power transmission and transformation project in Fengtai, Beijing is a key project of Beijing's power grid during the 15th Five-Year Plan period and one of the "3 100" key projects in Beijing this year. It is constructed and managed by the State
15 hours ago
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
15 hours ago
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Read More
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
Shaanxi-Anhui UHV DC Project's 500-kV AC System at Hezhou Station Begins Operation After Trial Run
On February 1st, the 500-kilovolt AC system of the Hezhou Converter Station, the receiving-end station of the ±800-kilovolt UHV DC power transmission project from northern Shaanxi to Anhui, was officially put into operation after a 24-hour trial run.
15 hours ago
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
15 hours ago
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
Read More
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
750-kV Power Line Connecting Northern to Central Shaanxi Fully Operational
On February 2nd, the 750-kilovolt power transmission and transformation project of the third passageway from northern Shaanxi to central Shaanxi was fully connected. The project starts from the 750-kilovolt Shuofang Substation in Shenmu City in the north and ends at the 750-kilovolt Bailuyuan Substation in Lantian County in the south. It has newly built a 1,271-kilometer line, passing through 18 counties (districts) in 4 cities including Yulin, Yan'an, Weinan and Xi'an.
15 hours ago