Home / Metal News / 0.5652~0.5658 yuan/Wh! The bidding for the 1.02 GWh standalone ESS EPC in Hebei has been opened!

0.5652~0.5658 yuan/Wh! The bidding for the 1.02 GWh standalone ESS EPC in Hebei has been opened!

iconMar 26, 2025 03:22
Source:SMM
【0.5652~0.5658 yuan/Wh! Hebei 1.02GWh Standalone ESS EPC Tender Opened!】Polaris ESS News: On March 25, the EPC tender for the Hebei Shangyi 300MW/1200MWh standalone ESS power station (Phase II) expansion project of 210MW/840MWh and 90MW/180MWh was opened. The total tender scale was 300MW/1020MWh, with the bid prices from the three consortiums ranging from 0.5652 to 0.5658 yuan/Wh. Moreover, subsidiaries of China Railway Group participated in all three consortiums.

Polaris Energy Storage News: On March 25, the EPC tender for the 210MW/840MWh and 90MW/180MWh expansion projects of the Hebei Shangyi 300MW/1200MWh standalone ESS power station (Phase II) was opened. The total tender scale was 300MW/1020MWh, with the bid prices of the three consortiums ranging from 0.5652 to 0.5658 yuan/Wh. Moreover, all three consortiums included subsidiaries of China Railway Group.

The first winning candidate was a consortium of Shanghai Electric Power Design Institute Co., Ltd. and China Railway Ninth Bureau Group Electric Engineering Co., Ltd., with a bid price of 576.981 million yuan, equivalent to a unit price of 0.5657 yuan/Wh.

The second winning candidate was a consortium of Sichuan Electric Power Design & Consulting Co., Ltd. and China Railway First Bureau Group Electric Engineering Co., Ltd., with a bid price of 576.4984 million yuan, equivalent to a unit price of 0.5652 yuan/Wh.

The third winning candidate was a consortium of PowerChina Jilin Electric Power Survey & Design Institute Co., Ltd. and China Railway 12th Bureau Group Electrification Engineering Co., Ltd., with a bid price of 577.1658 million yuan, equivalent to a unit price of 0.5658 yuan/Wh.

According to the previous tender, the project is located in Shangyi County, Zhangjiakou City, Hebei Province. This project involves the construction of a new 210MW/840MWh ESS power station in Phase II, while expanding the Phase I 90MW/180MWh ESS power station to 90MW/360MWh. The ESS battery uses LFP batteries, and both the battery system and power conversion system of the ESS station adopt an outdoor container layout scheme.

For queries, please contact William Gu at williamgu@smm.cn