Green Hydrogen Project Tracking—Mingyang Green Chemical (Chifeng) Co., Ltd. Annual Production of 1 Million mt Green Methanol Demonstration Project

iconMar 14, 2025 10:39
Source:SMM

Details of the Approval for the Industrial Project Filing of the Annual 1 Million mt Green Methanol Demonstration Project by Mingyang Green Chemical (Chifeng) Co., Ltd. (Development and Reform)

I. Basic Project Information

  • Project Name: Annual 1 Million mt Green Methanol Demonstration Project by Mingyang Green Chemical (Chifeng) Co., Ltd.
  • Project Entity: Mingyang Green Chemical (Chifeng) Co., Ltd.
  • Construction Location: Linxi Industrial Park, Chifeng Nonferrous Metal Development Zone, Linxi County, Chifeng City, Inner Mongolia
  • Total Investment: 6.7519799 billion yuan
  • Filing Dates: October 13, 2023 (official filing approval), March 13, 2025 (filing information reiterated)

II. Funding Sources

  • Self-Financing: 6.7519799 billion yuan
  • Bank Loan Application: 0 yuan
  • Other Funds: 0 yuan

III. Construction Scale and Content

  • Total Land Area: 526 mu
  • Total Building Area: 186,255 m², including 180,000 m² of newly constructed workshops and plants
  • Main Construction Content:
    1. Construction of new hydrogen production facilities via water electrolysis, biomass gasification units, methanol synthesis units, methanol distillation units, as well as utilities and auxiliary facilities.
    2. Construction of a 220kV step-down substation for the hydrogen production plant.
    3. Installation of 49 alkaline water electrolyzers with a capacity of 1,000 Nm³/h each and 2 units with a capacity of 2,000 Nm³/h.
    4. Construction of 2 methanol synthesis units with an annual capacity of 100,000 mt each.
    5. Construction of other supporting auxiliary facilities.

IV. Production Scale

  • Annual Green Hydrogen Production: 23,300 mt
  • Annual Green Methanol Production: 175,000 mt (synthesis)

V. Construction Schedule and Plan

  • Project Phases: The project will be constructed in two phases. Phase I will include the construction of a 600,000 mt/year methanol production line, and Phase II will include the construction of a 400,000 mt/year methanol production line.
  • Planned Construction Period: Dec 2023-Nov 2025

 

For queries, please contact William Gu at williamgu@smm.cn