[Rio Tinto and Edify Energy Sign Solar and ESS Agreement to Support Low-Carbon Transition in Aluminum Industry]

On March 12, 2025, Rio Tinto and Edify Energy signed an agreement under which Rio Tinto is expected to purchase 90% of the power and ESS capacity from the Smoky Creek and Guthrie’s Gap power stations over the next 20 years. The two stations have a total installed capacity of 600 MWac solar power and 600 MW/2,400 MWh ESS, with construction expected to begin by the end of 2025 and completion anticipated in 2028.

This project enables Rio Tinto to secure 2.7 GW of renewable energy in Queensland, which is expected to meet 80% of the power demand for the Boyne smelter and reduce carbon emissions by 70% (approximately 5.6 million mt). Rio Tinto holds 2,160 MWh of ESS capacity, ensuring stable power supply and enhancing power grid resilience.

데이터 출처 설명: 공개 정보를 제외한 모든 데이터는 SMM이 공개 정보, 시장 커뮤니케이션 및 SMM 내부 데이터베이스 모델을 기반으로 가공한 것입니다. 본 자료는 참고용이며 의사결정 권고를 구성하지 않습니다.

문의 사항이 있거나 자세한 정보를 원하시면 아래로 연락해 주시기 바랍니다: lemonzhao@smm.cn
리서치 보고서 열람 방법에 대한 자세한 내용은 아래로 문의하시기 바랍니다:service.en@smm.cn
[Rio Tinto and Edify Energy Sign Solar and ESS Agreement to Support Lo - Shanghai Metals Market (SMM)