On February 5, the winning bid result for the EPC general contracting of the Shandong Energy "Longdian into Shandong" supporting Baiyin New Energy Base Pingchuan Baoji 200MW PV Power Generation Project was announced. The winning consortium consists of Shandong Energy Group Construction Engineering Group Co., Ltd. and PowerChina Northwest Engineering Corporation Limited. The winning bid price is 509.9065951 million yuan, with a unit price of 2.089 yuan/W.
According to the bidding announcement, the project is located in Baoji Town, Pingchuan District, Baiyin City, Gansu Province. The total planned installed capacity is 200MW, with a DC side installed capacity of 244.05472MWp. The contractor is responsible for the procurement, expediting, and transportation of all necessary components for the project, including PV modules, inverters, brackets, box transformers, cables (including optical cables), cable terminals (intermediate) joints, 35kV collection lines, 110kV collection lines, a 110kV booster station, SVG, GIS, grid connection equipment (including but not limited to power forecasting equipment), computer monitoring and protection systems, supporting equipment for intelligent grid connection of the power station, communication, and metering equipment.
The planned start date is February 1, 2025, with the specific commencement date subject to the issuance of the commencement order by the supervising engineer.
The full-capacity grid connection date is expected to be before June 30, 2025.
The completion date is expected to be within 12 months after the full-capacity grid connection.
For queries, please contact William Gu at williamgu@smm.cn
For more information on how to access our research reports, please email service.en@smm.cn