Mongolia is considering ending its cooperation with Rio Tinto involving the world's largest copper and gold ore reserves of up to 30 million tons.

Published: Jan 13, 2021 17:11 (GMT+8)
Source: SMM compilation

According to a recent report, Turquoise Hill said that the Mongolian government may cancel and replace the development and financial plans of the country's huge Oyu Tolgoi copper and gold mine. The company, controlled by Rio Tinto, said the Mongolian authorities were not satisfied with the plans of the top mining company. They are particularly concerned about the cost of the expansion, which was recently updated to $6.75 billion, $1.5 billion higher than the original estimate.

Turquoise Hill said Mongolia believed that the sharp rise in costs had eroded the expected economic benefits from the Oyu Tolgoi mine. The company's share price fell to its lowest level in a month after the news. Rio (Rio Tinto) (pointed out the stability risks associated with the original project design in 2019, implying up to $1.9 billion in additional costs and a 30-month delay.

The miner confirmed new cost estimates for underground expansion in December, adding that production would begin in October 2022. Erdenes Oyu Tolgoi LLC, a Mongolian company with 1/3 mines, responded to the new timetable and budget, saying Rio Tinto had failed to deliver on its 2015 commitments.

Erdenes's stake in Oyu Tolgoi is technically 34 per cent held through Oyu Tolgoi LLC, a Mongolian company. The rest belongs to Canada's Turquoise Hill Resources, which is 50.79 per cent owned by Rio Tinto.

"the Mongolian government has made it clear that if the Oyu Tolgoi project has no economic benefit to the country, it is necessary to review and assess whether the project can continue," Turquoise Hill said in a statement.

Ulaanbaatar also said that Oyu Tolgoi was expected to pay corporate income tax or profits tax only in the four years up to 2051, raising doubts about the economic benefits of the project. "it is estimated that the government will never receive) dividends from the (Oyu Tolgoi project and will assume $22 billion in debt, which will bring great difficulties to our future cooperation," it said in a letter quoted by Turquoise Hill.

The Vancouver-based mining company said it was committed to immediately reaching out to the Mongolian authorities and Rio Tinto to resolve the development plan and reconsider sharing the economic benefits of the Oyu Tolgoi project.

According to public data, among the proven minerals, Mongolia's Oyu Tolgoi project is one of the largest copper and gold deposits in the world, with copper reserves of 31.1 million tons, gold reserves of 1328 tons and silver reserves of 7600 tons. After the successful completion of the underground mining project, it is expected to contribute 20 per cent of Rio Tinto's revenue a year.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Peru sees 1 million t/y copper output boost within five to six years
20 hours ago
Peru sees 1 million t/y copper output boost within five to six years
Read More
Peru sees 1 million t/y copper output boost within five to six years
Peru sees 1 million t/y copper output boost within five to six years
Peru's Energy and Mines Minister Guillermo Shinno said the country expects to add about 1 million tonnes of annual copper production within five to six years through new mining projects. The world's third-largest copper producer anticipates 2026 output of 2.5 to 2.7 million tonnes, roughly unchanged from 2023 as declining ore grades and recurring social conflicts weigh on supply. The newly elected government is seeking to reverse that stagnation by cutting red tape; in the two months since taking office, mining companies have stepped up engagement with the ministry. Shinno said officials have identified 27 permits that could be eliminated from roughly 100 mining-sector requirements, without lowering environmenta
20 hours ago
India copper producers seek GST cut as record prices raise working-capital burden
Sep 25, 2026 20:26 (GMT+8)
India copper producers seek GST cut as record prices raise working-capital burden
Read More
India copper producers seek GST cut as record prices raise working-capital burden
India copper producers seek GST cut as record prices raise working-capital burden
Indian copper producers are seeking a GST cut to 5% from 18%, citing rising working-capital requirements amid record-high copper prices.
Sep 25, 2026 20:26 (GMT+8)
Sulphuric Acid Shortage Emerges as a Constraint on Zambia’s Copper Growth
Sep 25, 2026 16:43 (GMT+8)
Sulphuric Acid Shortage Emerges as a Constraint on Zambia’s Copper Growth
Read More
Sulphuric Acid Shortage Emerges as a Constraint on Zambia’s Copper Growth
Sulphuric Acid Shortage Emerges as a Constraint on Zambia’s Copper Growth
Zambia’s sulphuric acid shortage is becoming a growing constraint on copper production and refining. Jubilee Metals reported acid costs rising by more than 200% in Q4 FY2026, while Sable cathode output fell to 250 t from 361 t in Q3. Government data also showed small-scale copper production down 35.2% YoY in H1 2026, highlighting the sector’s exposure to tight acid availability and higher processing costs.
Sep 25, 2026 16:43 (GMT+8)