[2019.07.04 Cobalt Lithium New Energy Internal Morning meeting Summary] large area reduction in Cobalt Lithium production of Power batteries prices fell across the board

Published: Jul 4, 2019 10:38

SMM 04 / 07 / 04 / PRNewswire-Asianet /-

Battery Terminal Market:

The power battery market has seen a large reduction in production since June. On the demand side, the downstream market entered a period of downturn, and the growth rate of new energy vehicles slowed down in the second quarter, affected by the decline of subsidized slopes and the removal of "national five" models to the warehouse. In May, the year-on-year growth rate of new energy vehicles reached its lowest point in recent years. After the formal end of the subsidy transition period on June 25, some models will plan to adjust prices, and the high temperature leave of the mainframe factory in July and August will affect some production, and the overall market situation is expected to remain depressed in the third quarter.

Upstream raw material price:

Cobalt: this week, the domestic cobalt market prices fell significantly, metal cobalt and derivatives fell across the board, last night foreign media quotations hit a new low in 2019, fell through the psychological defense line of some market people, pessimism ferments strongly. SMM expects the cobalt market trading price to be low or 170000 yuan per ton in the short term, and the cobalt premium will continue to narrow.

Lithium: demand for battery-grade lithium carbonate has fallen sharply recently. In response to market changes, businesses have chosen to cut prices. Compared with battery-grade lithium carbonate, the demand for industrial-grade lithium carbonate has also weakened, but the change is not as obvious as the demand for battery-grade lithium carbonate. Some battery-grade lithium carbonate manufacturers are also trying to make production adjustments to increase the share of industrial lithium carbonate sales to maintain production. Lithium iron phosphate: power lithium iron phosphate production enterprises said that due to the impact of production cuts in enterprises C and B, orders were significantly reduced in June. Orders are expected to be slightly better in July than in the previous month, but overall performance in the third quarter was disappointing. For the order performance of lithium iron phosphate, the overall performance is relatively stable.

 

SMM Cobalt Lithium Research team

Hong Lu 021 51666814

Ning Ziwei 021 51666780

Qin Jingjing 021 51666828

Long press attention

Learn more about the highlights

 

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Baota Mountain Converter Station's AC System Energized, Marking Key Milestone in UHV Project
20 hours ago
Baota Mountain Converter Station's AC System Energized, Marking Key Milestone in UHV Project
Read More
Baota Mountain Converter Station's AC System Energized, Marking Key Milestone in UHV Project
Baota Mountain Converter Station's AC System Energized, Marking Key Milestone in UHV Project
On February 5, the AC system of the Baota Mountain Converter Station, the sending - end station of the ±800 kV North Shaanxi - Anhui UHV DC power transmission project, was successfully energized for the first time. This marks that the AC system of the converter station has entered the startup commissioning stage, and the entire AC system of the project is expected to be put into operation before the Spring Festival. It is reported that the rated voltage of the North Shaanxi - Anhui UHV project is ±800 kV, with a rated capacity of 8 million kilowatts, and a dynamic investment of 20.5 billion yuan. The project starts from the Baota Mountain Converter Station in Yan'an City, Shaanxi Province, and ends at the Hezhou Converter Station in Hefei City, Anhui Province. It passes through three provi
20 hours ago
World's First Multi-Source DC Project in Jiangsu Completes Phase II, Boosts Cross-River Power Transmission
20 hours ago
World's First Multi-Source DC Project in Jiangsu Completes Phase II, Boosts Cross-River Power Transmission
Read More
World's First Multi-Source DC Project in Jiangsu Completes Phase II, Boosts Cross-River Power Transmission
World's First Multi-Source DC Project in Jiangsu Completes Phase II, Boosts Cross-River Power Transmission
On February 12, the second - phase project of the ±200 kV DC power transmission project from Yangzhou to Zhenjiang in Jiangsu, which is the world's first multi - source commutated DC power transmission project and China's first AC - DC hybrid cross - river project, was completed and put into operation. The project's transmission line is about 228 kilometers long, with a transmission capacity of 1.2 million kilowatts. It passes through three cities (Huai'an, Yangzhou, and Zhenjiang) and seven counties. Among them, a 47 - kilometer new - built DC transmission line is erected on the same tower as the 500 kV AC line, and two new converter stations are built. Without adding a new cross - Yangtze - River power transmission channel, the original cross - river power transmission capacity has been
20 hours ago
Shaanxi Boosts Power Capacity to 127GW, Invests in Grid and Renewable Energy Growth
20 hours ago
Shaanxi Boosts Power Capacity to 127GW, Invests in Grid and Renewable Energy Growth
Read More
Shaanxi Boosts Power Capacity to 127GW, Invests in Grid and Renewable Energy Growth
Shaanxi Boosts Power Capacity to 127GW, Invests in Grid and Renewable Energy Growth
It is learned that Shaanxi Province's power generation installed capacity has increased from 72.75 million kilowatts in 2020 to 127 million kilowatts in 2025, with the installed capacity of renewable energy growing by about 2.7 times. Meanwhile, the province has invested a total of 120 billion yuan to strengthen the power grid and expand transmission channels, making the power grid more robust and reliable. Statistics show that during the 14th Five-Year Plan period, Shaanxi put into operation over 10 million kilowatts of clean and efficient coal-fired power generation capacity, and the scale of coal-fired power projects under construction that meet regulations reached a record high for the same period. The total scale of coal-fired power plants undergoing energy-saving and carbon-reduction
20 hours ago