SMM Network News: 1. Stainless Steel Heat treatment Project of Fujian Qingtuo Industrial Co., Ltd.

Nature of the project: expansion

Industry category: C3360 metal surface treatment and heat treatment

Construction site: Wan Wu Zhen Sha Wan Cun, Fu'an City

Construction scale: annual heat treatment of 530000 tons of stainless steel products

Construction content: construction of 2 annular solid solution furnaces, 20 bell annealing furnaces and 4 trolley solid melting furnaces, annual heat treatment of 530000 tons of stainless steel products, At the same time, we will build three Φ 4.2m two-stage gas generators, electrical facilities, water treatment and related public auxiliary facilities.

Construction cycle: the project construction cycle is 18 months, from June 2019 to December 2020.

Investment: the total investment in the project is 200 million yuan, of which the investment in environmental protection is 14.82 million yuan, accounting for 7.4% of the total investment in the project.

Production system: the production workshop adopts three shifts of continuous work system, each shift 8 hours, working time 300 days.

Labor fixed staff: the new labor staff of the project is about 85, of which 80 are production workers and 5 are managers.

After the completion of the project, the annual processing of 530000 tons of stainless steel products, the main production products include stainless steel wire and stainless steel bar profiles.

II. Fujian Qingtuo equipment Manufacturing Co., Ltd. Metallurgical equipment and Accessories Manufacturing Project

Project nature: new

Industry category: C3516 special equipment for metallurgy

Construction site: Longzhu Village, Wanwu Town, Fu'an City, located east of Grade II Road on the south side of Dingxin Industrial Office Building (Longzhu Village)

Construction scale: annual output of 6000 tons of finishing products

Construction cycle: the project construction cycle is 4 months, from June 2019 to October 2019.

Investment: the total investment in the project is 118 million yuan, of which the investment in environmental protection is 500000 yuan, accounting for 0.42% of the total investment in the project.

Production system: single shift production, each shift 8 hours, working hours 280 days.

Labor personnel: the number of project personnel is 75.

After the completion of the project, it is mainly engaged in the production and manufacture of metallurgical equipment and accessories, including finishing products, flanges, continuous casting rollers and other products.

"[investment must see] Trade friction news flying all over the metal how to win in chaos?

"Click to enter the registration page

Scan QR code and apply to join SMM metal exchange group, please indicate company + name + main business

 

Steel
stainless steel

For queries, please contact Michael Jiang at michaeljiang@smm.cn

For more information on how to access our research reports, please email service.en@smm.cn

Related news