SHANGHAI, Sept. 5 (SMM) –The table below shows unit maintenance schedules at some domestic steel mills.
Region |
Steel Mill |
Maintenance Period |
Output Loss |
Products Affected |
Units under Maintenance |
Northeast China |
Ansteel |
10 days from Sept. 1-10 |
50,000 tonnes |
hot-rolled |
1,700 m3 |
Northeast China |
Ansteel |
62 days from Sept. 15 |
55,800 tonnes |
hot-rolled |
4,083 m3 |
East China |
Laiwu I&S |
4 months from Sept. 20 |
720,000 tonnes |
hot-rolled |
1,880 m3 |
East China |
Laiwu I&S |
4 months from Sept. 28 |
720,000 tonnes |
hot-rolled |
1,700 m3 |
Northwest China |
Baogang Group |
15 days from Oct. 1-15 |
150,000 tonnes |
hot-rolled |
2,250 m3 |
East China |
Jinan I&S |
to restart production in late Sept. |
180,000-200,000 tonnes |
hot-rolled |
closing in early July for capacity swap |
Southwest China |
Panzhihua I&S |
1 month from Aug. 4 to Sept. 4 |
4,500 tonnes |
liquid iron |
1,750 m3 |
Northeast China |
Benxi Steel Group |
to restart production from Sept. 16 |
150,000 tonnes |
liquid iron |
#1 4,747 m3 |
Northeast China |
Benxi Steel Group |
to restart production Oct. 15 |
270,000 tonnes |
liquid iron |
#7 2,850 m3 |
East China |
Masteel |
from Jul. 11 to early Oct. |
8,000 t/d |
liquid iron |
4,000 m3 |
West China |
Xinjiang Bayi I&S |
20 days from Aug. 30 to Sept. 20 |
60,000 tonnes |
liquid iron |
3,000 m3 |
North China |
Tiantie Group |
22 days from Sept. 4-25 |
136,400 tonnes |
liquid iron |
2,800 m3 |
East China |
Huaigang Special Steel |
1 month from Sept. 5 to Oct. 5 |
35,000 tonnes |
bar |
530 m3 |
North China |
Xuansteel |
12 days from Sept. 1 to 12 |
17,000 tonnes |
bar |
|
North China |
Chengde Jianlong Special Steel |
1 day on Sept. 10 |
3,000 tonnes |
bar |
|
East China |
Shagang Group Yongxing I&S |
already resuming production |
already resuming production |
bar |
line 1 and 2 |
East China |
Fujian Sanbao Steel |
4 days |
15,000 tonnes |
bar |
bar line |
East China |
Shandong LaiGang Yongfeng I&S |
resuming production on Aug. 24 |
40,000 tonnes |
bar |
bars in coil |
Southwest China |
Chengyu Vanadium & Titanium Technology |
2 days |
3,000 tonnes |
|
|
North China |
Two mills in Xiangfen |
2 days |
18,000 tonnes |
|
|
East China |
Quzhou Yuanli Steel |
10 days from Aug. 31 to Sept. 10 |
25,000-30,000 tonnes |
bar |
|
East China |
Rizhao I&S |
10 days from Sept. 10 to 20 |
30,000 tonnes |
section |
|
For news cooperation, please contact us by email: sallyzhang@smm.cn or service.en@smm.cn.
For queries, please contact William Gu at williamgu@smm.cn
For more information on how to access our research reports, please email service.en@smm.cn