Australia's Endeavor Silver-Zinc Mine Approaches Restart, Commissioning Slated for April 2025

게시됨: Apr 3, 2025 23:19

[Australia’s Endeavor Silver-Zinc Mine Nearing Restart]

On April 2nd, Polymetals Resources Ltd announced that its Endeavor Silver-Zinc Mine in New South Wales, Australia is nearing a restart, with commissioning activities scheduled to begin in April 2025 and first ore processing and concentrate production expected in May. Furthermore, the company anticipates generating initial cash flow within the current quarter.

During the March 2024 quarter, several key underground development milestones were achieved. First ore has already been stockpiled underground in preparation for crushing and hoisting activities planned for May. At the same time, upgrades to the ventilation system, as well as commissioning of production drill rigs, loaders, and other mobile equipment, continued in line with the Mine Restart Plan. On the surface, critical refurbishment works at the processing plant are also progressing, including repairs to the SAG and ball mills, and replacement of the mill feed infrastructure. Once fully operational, the plant will have a processing capacity of 1.2 million tonnes of ore per annum.

As of 2023, the mine reports 13.2 million tonnes of Measured and Indicated Resources, with average grades of zinc and lead at 8.1% and 4.7% respectively.

데이터 출처 설명: 공개 정보를 제외한 모든 데이터는 SMM이 공개 정보, 시장 커뮤니케이션 및 SMM 내부 데이터베이스 모델을 기반으로 가공한 것입니다. 본 자료는 참고용이며 의사결정 권고를 구성하지 않습니다.

문의 사항이 있거나 자세한 정보를 원하시면 아래로 연락해 주시기 바랍니다: lemonzhao@smm.cn
리서치 보고서 열람 방법에 대한 자세한 내용은 아래로 문의하시기 바랍니다:service.en@smm.cn
[Australia’s Endeavor Silver-Zinc Mine Nearing Restart] On April 2nd, - Shanghai Metals Market (SMM)