Inalum to Start Second Phase of Mempawah Alumina Refinery in West Kalimantan by 2025

게시됨: Mar 31, 2025 16:41

Indonesia's Inalum is expected to commence the second phase of construction at the Mempawah metallurgical-grade alumina refinery (SGAR) in West Kalimantan in 2025. Currently, the company anticipates completing the feasibility study and final investment decision (FID) within 2024, which will serve as the foundation for subsequent engineering, procurement, and construction (EPC) activities.

Inalum, in collaboration with Indonesia's state-owned miner PT Aneka Tambang (Antam), has completed the first phase of the project, which is expected to achieve full production capacity by the end of Q1 2025, with an annual capacity of 1 million mt. Upon completion of the second phase, the total capacity will double to 2 million mt per year.

데이터 출처 설명: 공개 정보를 제외한 모든 데이터는 SMM이 공개 정보, 시장 커뮤니케이션 및 SMM 내부 데이터베이스 모델을 기반으로 가공한 것입니다. 본 자료는 참고용이며 의사결정 권고를 구성하지 않습니다.

문의 사항이 있거나 자세한 정보를 원하시면 아래로 연락해 주시기 바랍니다: lemonzhao@smm.cn
리서치 보고서 열람 방법에 대한 자세한 내용은 아래로 문의하시기 바랍니다:service.en@smm.cn