State Power Hebei Company's Dingzhou Power Plant Phase III Expansion Project, including the construction of two 660MW units and their auxiliary equipment, and the Cangdong Power Plant Phase III Expansion Project, including the construction of two 660MW units and their auxiliary equipment, have announced the shortlisted candidates for the bid.
The shortlisted candidates are:
- Harbin Turbine Co., Ltd., with a bid price of 1,273.04 million RMB
- Dongfang Electric Corporation, Dongfang Turbine Co., Ltd., with a bid price of 1,299.80 million RMB

![[ SMM 분석 ] 19개 구리 제련소의 2026년 반기 보고서 한눈에 보기](https://imgqn.smm.cn/usercenter/gCNEi20251217171715.jpeg)