"North Star Power Transmission and Distribution Network has learned that the Beijing Development and Reform Commission has approved the CBD 500 kV substation 220 kV outbound project. The project details are as follows:
Project Name: CBD 500 kV Substation 220 kV Outbound Project.
Construction Unit: State Grid Beijing Power Company.
Construction Site: CBD area in Chaoyang District.
Construction Content and Scale: Use the existing tunnel to build a new cable route with a total length of approximately 31.26 kilometers.
Investment Situation: The total investment of the project is 379.51 million yuan. All of which will be self-financed by State Grid Beijing Power Company."