Everbright Environmental Jiangsu Huai'an 2.5MW/5MWh Zero Carbon Park Energy Storage Project Design and Construction General Contract Termination
On January 23rd, Everbright Environmental issued a termination notice for the design and construction general contract of the energy storage project in the South Factory Area of the Zero Carbon Park. The notice stated that as of the bid deadline, there were fewer than 3 bidders submitting bid documents, resulting in the termination of the project bidding. It will be re-tendered at a later date.