Musk encounters "pig teammates": the supply of tens of thousands of tons of lithium ore has been postponed indefinitely

Telah Terbit: Aug 12, 2021 16:55
[Musk encounters "pig teammates": the supply of tens of thousands of tons of lithium ore has been postponed indefinitely.] in September last year, Tesla CEO Musk proudly announced that he would produce lithium electricity at the Battery Day, and a few days later signed a five-year lithium supply contract with Australian lithium miner Piedmont (Piedmont). The news almost immediately spurred Piedmont's share price to soar several times.

Last September, Tesla CEO Musk proudly announced that he would produce lithium electricity at Battery Day, and a few days later signed a five-year lithium supply contract with Australian lithium miner Piedmont (Piedmont). The news almost immediately spurred Piedmont's share price to soar several times.

Musk's vision is good: Piedmont owns a huge lithium mine in North Carolina, and when completed, the mine will become the largest lithium project in the United States and can supply 53000 tons of lithium concentrate to Tesla. Tesla will build a lithium smelter near the Texas super factory to refine the lithium concentrate into lithium hydroxide for battery production to solve Tesla's shortage of lithium power.

Nearly a year later, however, Piedmont's lithium mine project in North Carolina has made no progress. Last week, Piedmont announced that it would indefinitely delay the delivery of the first spodumene concentrate to Tesla, meaning that Musk's ambition to produce lithium electricity was poured cold water on the first step.

The trouble caused by the company's "procrastination"

According to the original agreement, Piedmont was supposed to deliver the first shipment between July 2022 and July 2023. But Piedmont now faces an awkward dilemma-local approvals cannot be done.

However, the problem can not be blamed for the strict approval of the local government, it is all the fault of Piedmont himself.

As early as September 2018, Piedmont disclosed to investors that the company would apply for a mining license in local Gaston County for the project, which is expected to be available in 2019. But in fact, the company has been slow to act.

In August 2019, executives said again that they "expect to get permission in the next few months". But it turned out to be empty talk.

The explanation given by the company's executives seems innocent: they do not know the reason why the county committee did not approve it.

The Gaston county committee, which is responsible for approving the project, is angry. They said they specifically asked Piedmont to inform them of the possible dust, noise and vibration caused by the mining project, as well as the possible impact of the mining project on local water and air quality. but the company did not provide any relevant information at all.

In fact, the real reason for the company's delay in submitting applications may be the weak price of lithium ore in the past two years, so the company is in no hurry to apply for permission.

But the problem is that repeated delays have seriously worsened the relationship between the company and the local government, especially when Piedmont announced a high-profile cooperation agreement with Tesla last fall, which made county committee members feel even more incredible. The chairman of the county committee said bluntly: "Why did Piedmont reach an agreement with Tesla before the mine was approved?" This is completely putting the cart before the horse. "

At present, five of the seven members of the county committee responsible for approving the project have publicly indicated that they will reject or postpone the project, and one of them said bluntly: "I have never seen a company start a project so badly."

News of the impasse in the mining project also triggered a plunge in the company's share price of more than 20% in July, followed by a class action lawsuit by investors, accusing executives of misleading investors about the project development timetable.

The date of mine approval is a long way off.

In July, the first meeting between Piedmont and the county council finally came long overdue. At the online meeting, Piedmont CEO Phillips finally introduced the details of the lithium mine project to the county committee members for the first time and sincerely apologized, saying bluntly that it was "all my fault" that he did not maintain a good relationship with the community.

However, the county council may still be unconvinced, because Piedmont has been in conflict with some local residents in the process of land expansion in western Gaston County over the past two or three years.

Some residents complained that Piedmont made them angry by trying to force them to buy land through threats. In addition, the possible noise pollution caused by the Piedmont mine also worries local residents. By the end of July, more than 1500 local people had signed a petition asking officials to stop the mine project.

On August 6, the county committee adopted a resolution saying that the company "cannot take sufficient measures to protect the health, safety and welfare of its citizens and cannot be trusted." At the same time, the county committee also issued a 60-day mining ban, during which time the county committee will review local industry regulations.

As a result, Piedmont had to announce that the delivery of lithium ore to Tesla could only be postponed indefinitely.

On Monday, Piedmont CEO said it was conducting a final feasibility study on its lithium business in the region, which is expected to be completed in the second half of this year. The company CEO stressed in the announcement: "the resolution of the Gaston county committee is not intended to stop mining, but to give the county time for transfer and review." We look forward to more contacts with the county committee on its commitment to promote environmental protection and economic prosperity in the county. "

However, North Carolina officials expect the review to last more than a year. And even if the company gets the permit, it will have to apply to the North Carolina government for "rezoning" and other procedures after that before the mine can start construction. It often takes more than a year and a half for a lithium mine to go into production-which means it may be a long way off.

Pernyataan Sumber Data: Kecuali informasi yang tersedia untuk publik, semua data lainnya diproses oleh SMM berdasarkan informasi publik, komunikasi pasar, dan mengandalkan model database internal SMM. Hanya untuk referensi dan tidak menjadi rekomendasi pengambilan keputusan.

Untuk pertanyaan atau informasi lebih lanjut, silakan hubungi: lemonzhao@smm.cn
Untuk informasi lebih lanjut tentang cara mengakses laporan penelitian kami, hubungi:service.en@smm.cn
Berita Terkait
[Baterai solid-state: produksi elektrolit sulfida 70 mt, Januari-Agustus]
1 jam yang lalu
[Baterai solid-state: produksi elektrolit sulfida 70 mt, Januari-Agustus]
Baca Selengkapnya
[Baterai solid-state: produksi elektrolit sulfida 70 mt, Januari-Agustus]
[Baterai solid-state: produksi elektrolit sulfida 70 mt, Januari-Agustus]
[Baterai solid-state: Produksi elektrolit sulfida 70 mt pada Januari-Agustus] Dari Januari hingga Agustus 2026, produksi elektrolit sulfida kumulatif Tiongkok mencapai 70 mt, naik 119,7% YoY, sudah melampaui total setahun penuh 2025 (58,29 mt). Namun, pertumbuhan mengesankan ini menutupi tiga kenyataan pahit: ① Hanya 19,6% dari target perkiraan tahunan (360 mt) yang tercapai; ② Tingkat utilisasi kapasitas pada Agustus hanya 5,82%, dengan kapasitas yang menganggur parah; ③ Harga produk terus merosot (LPSC turun lebih dari 24% dalam satu bulan). Produksi rata-rata bulanan Q4 kemungkinan besar berada di kisaran 11,5-13 mt, dengan total setahun penuh sekitar 118-121 mt, yang merupakan "pendakian solid." Perkiraan tahunan 360 mt, dengan hanya 70 mt yang diselesaikan dalam delapan bulan pertama: kesenjangan antara "peningkatan bertahap" elektrolit sulfida Tiongkok dan kenyataan.
1 jam yang lalu
[SMM Analysis] Eropa Mencari Kemandirian Rantai Pasokan Litium, Namun Proyek-Proyeknya Menarik Investor Asia
1 jam yang lalu
[SMM Analysis] Eropa Mencari Kemandirian Rantai Pasokan Litium, Namun Proyek-Proyeknya Menarik Investor Asia
Baca Selengkapnya
[SMM Analysis] Eropa Mencari Kemandirian Rantai Pasokan Litium, Namun Proyek-Proyeknya Menarik Investor Asia
[SMM Analysis] Eropa Mencari Kemandirian Rantai Pasokan Litium, Namun Proyek-Proyeknya Menarik Investor Asia
1 jam yang lalu
Proyek Tembaga-Emas-Kobalt Farellon di Chili Menyelesaikan Pengiriman Bijih Pertama, Memulai Produksi Skala Kecil
2 jam yang lalu
Proyek Tembaga-Emas-Kobalt Farellon di Chili Menyelesaikan Pengiriman Bijih Pertama, Memulai Produksi Skala Kecil
Baca Selengkapnya
Proyek Tembaga-Emas-Kobalt Farellon di Chili Menyelesaikan Pengiriman Bijih Pertama, Memulai Produksi Skala Kecil
Proyek Tembaga-Emas-Kobalt Farellon di Chili Menyelesaikan Pengiriman Bijih Pertama, Memulai Produksi Skala Kecil
Menurut Red Metal Resources pada 3 September, proyek Farellon, bagian dari properti tembaga-emas-kobalt Carrizal milik perusahaan di dekat Vallenar, Chili, telah menyelesaikan pengiriman pertama bijih tembaga sulfida, menandai transisi proyek dari tahap pengembangan ke penjualan bijih aktual dan produksi skala kecil. Penyewa dan operator proyek, Minera KMT, mengangkut batch bijih pertama ke fasilitas pemrosesan Vallenar yang dioperasikan oleh perusahaan pertambangan milik negara Chili, ENAMI, pada 20 dan 21 Agustus. Tonggak ini tercapai hanya sekitar tiga bulan setelah para pihak menandatangani perjanjian pertambangan pada bulan Mei, sekitar empat bulan lebih cepat dari jadwal pengembangan awal tujuh bulan. Farellon adalah bagian penting dari properti tembaga-emas-kobalt Carrizal. Pengiriman bijih pertama diharapkan menghasilkan pendapatan royalti bagi Red Metal dan menjadi dasar untuk perluasan lebih lanjut aktivitas penambangan dan pemrosesan. Perusahaan belum mengungkapkan kadar kobalt spesifik, output kobalt, atau tingkat pemulihan untuk bijih yang dikirim. Namun, langkah proyek menuju produksi dan penjualan aktual merupakan perkembangan baru dalam jalur sumber daya kobalt Chili di luar Afrika.
2 jam yang lalu