Production Update of Tsingshan Phase Two Project in Indonesia, SMM Reports

Telah Terbit: Mar 22, 2016 10:57
Tsingshan Group has put online its whole phase two project, with total capacity of 60,000-tpy (metal content), in Indonesia recently, SMM learns.

SHANGHAI, Mar. 22 (SMM) – Tsingshan Group has put online its whole phase two project, with total capacity of 60,000-tpy (metal content), in Indonesia recently, SMM learns.  

Tsingshan Group started production at its phase two project last December, but power supply issues restricted its production capacity, only 30,000-tpy capacity online. 

This March, the Group succeeded to produce from the rest of the project, SMM learns.  

Tsingshan Group started its trial production at its phase one project in January 2015, producing 20,000 tonnes (metal content) over the year, and will complete construction of phase three project in 2017, according to its plan.  

For news cooperation, please contact us by email: sallyzhang@smm.cn or service.en@smm.cn.

Pernyataan Sumber Data: Kecuali informasi yang tersedia untuk publik, semua data lainnya diproses oleh SMM berdasarkan informasi publik, komunikasi pasar, dan mengandalkan model database internal SMM. Hanya untuk referensi dan tidak menjadi rekomendasi pengambilan keputusan.

Untuk pertanyaan atau informasi lebih lanjut, silakan hubungi: lemonzhao@smm.cn
Untuk informasi lebih lanjut tentang cara mengakses laporan penelitian kami, hubungi:service.en@smm.cn