Nanchang's 1000-kV UHV Substation Expansion 40% Complete, Set for September Launch

Published: Feb 14, 2026 20:18
On February 4, the main transformer expansion project of the 1000-kilovolt UHV substation in Nanchang has currently completed 40% of the total project volume, and both the equipment foundation pouring and the overhead framework hoisting operations are nearing completion. After the Spring Festival, equipment installation and commissioning work will be fully carried out to ensure the project is successfully completed and put into use in September this year.
It is reported that this project is a key UHV main transformer project in Jiangxi Province's 14th Five-Year Plan. The construction scope includes adding one set of 3000 MVA main transformers, one set of 1000-kV switches, four sets of 500-kV switches, and four sets of low-voltage reactive power compensation devices, etc. The total project

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn