Ivanhoe Electric Raises Santa Cruz Copper Output Profile as Initial Capex Climbs to US$1.43 Billion

Published: Sep 24, 2026 15:18 (GMT+8)

Ivanhoe Electric has completed an updated Preliminary Feasibility Study (PFS) for its 100%-owned Santa Cruz Copper Project in Arizona, outlining a faster production ramp-up and higher copper output while increasing initial capital expenditure and pushing first copper cathode production to 2029.​

According to the September 23 study, Santa Cruz is expected to produce an average of approximately 75,000 mt/year of copper cathode during its first 15 years of operation. The optimized mine plan incorporates a faster production ramp-up compared with the 2025 PFS, supported by changes to mine access, material handling and paste backfill design.​

Initial project capital is now estimated at US$1.43 billion, compared with US$1.24 billion in the 2025 PFS. Ivanhoe Electric attributed the increase partly to inflation in construction materials and labour, as well as updated engineering for mine development, ventilation shafts, tunnel access and changes to the surface processing facilities.​

Life-of-mine C1 cash costs are estimated at US$1.47/lb of copper, up from US$1.32/lb in the previous study, while all-in sustaining costs are estimated at US$2.28/lb. The project is expected to achieve an average life-of-mine copper recovery of 92.3%.​

Santa Cruz is designed as an underground operation using heap leaching and downstream processing to produce 99.99% pure copper cathode on site without requiring external smelting. The updated study supports a 24-year mine life.​

Early site preparation and development activities have commenced, with box-cut development expected to begin in October 2026 and tunnel-boring-machine decline development targeted for summer 2027. First copper cathode production is now targeted for 2029, compared with the 2028 target outlined in the 2025 PFS.​

The updated PFS presents a higher copper production profile for Santa Cruz but also reflects increased development costs and a later first-production schedule. The approximately US$190 million increase in initial capital and higher operating costs reflect inflation and further engineering work as the project advances toward development. Meanwhile, the optimized mine plan raises average copper cathode production during the first 15 years to approximately 75,000 mt/year. With early development activities underway, attention will now turn to execution of the underground development programme, project financing and progress toward first copper production in 2029.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Gunnison Copper's Johnson Camp Mine Achieves Commercial Production, Ramp-Up Continues
1 min ago
Gunnison Copper's Johnson Camp Mine Achieves Commercial Production, Ramp-Up Continues
Read More
Gunnison Copper's Johnson Camp Mine Achieves Commercial Production, Ramp-Up Continues
Gunnison Copper's Johnson Camp Mine Achieves Commercial Production, Ramp-Up Continues
Gunnison Copper announced that its Johnson Camp Mine in Arizona achieved commercial production in September 2026, following record monthly copper cathode production in August and sustained operations above the company's required operating threshold during the first half of September.​ Johnson Camp produced 1.30 million lb, or approximately 592 mt, of copper cathode in August, marking its highest monthly production since operations restarted. The mine subsequently produced another 894,767 lb, or approximately 406 mt, of copper cathode between September 1 and September 17.​ Gunnison said the sustained operating performance in September supported its determination that Johnson Camp had reached commercial production. The operation is continuing to ramp up toward its nameplate production capacity of up to 25 million lb/year, equivalent to approximately 11,340 mt/year, of copper cathode.​ Johnson Camp produces 99.999% pure copper cathode directly from ore mined in Arizona, with copper processed into finished cathode at the site without requiring external smelting and refining. The operation is fully funded by Nuton LLC, a Rio Tinto venture.​ The achievement of commercial production follows the restart and subsequent ramp-up of Johnson Camp, while Gunnison continues to advance its larger flagship Gunnison Copper Project in Arizona.​ The achievement of commercial production at Johnson Camp marks a further step in the ramp-up of US domestic copper supply. August production reached a record level since the restart, while sustained output through the first half of September supported the company's declaration of commercial production. Attention will now turn to the pace of the remaining ramp-up toward the mine's nameplate copper cathode capacity of approximately 11,340 mt/year.
1 min ago
Copper Cathode Rod Producers' Operating Rates Up 4.08% WoW, Down 3.88% YoY Amid Pre-Holiday Stockpiling
3 mins ago
Copper Cathode Rod Producers' Operating Rates Up 4.08% WoW, Down 3.88% YoY Amid Pre-Holiday Stockpiling
Read More
Copper Cathode Rod Producers' Operating Rates Up 4.08% WoW, Down 3.88% YoY Amid Pre-Holiday Stockpiling
Copper Cathode Rod Producers' Operating Rates Up 4.08% WoW, Down 3.88% YoY Amid Pre-Holiday Stockpiling
[SMM Copper Cathode Rod Flash] Operating rates of copper cathode rod producers rose 4.08 percentage points WoW this week, but fell 3.88 percentage points YoY. Pre-holiday stockpiling orders provided the main support, as operating rates continued to rebound.
3 mins ago
Downstream active restocking during the Mid-Autumn Festival and National Day holiday drove spot premiums sharply higher; premiums are expected to decline next week [SMM South China copper cathode spot weekly review]
5 mins ago
Downstream active restocking during the Mid-Autumn Festival and National Day holiday drove spot premiums sharply higher; premiums are expected to decline next week [SMM South China copper cathode spot weekly review]
Read More
Downstream active restocking during the Mid-Autumn Festival and National Day holiday drove spot premiums sharply higher; premiums are expected to decline next week [SMM South China copper cathode spot weekly review]
Downstream active restocking during the Mid-Autumn Festival and National Day holiday drove spot premiums sharply higher; premiums are expected to decline next week [SMM South China copper cathode spot weekly review]
5 mins ago