The new project is put into production! Tongling Nonferrous will build the largest single Mine Copper smelting Plant in China

Published: Jun 18, 2020 13:12
[new project put into production! Tongling Nonferrous will build the largest single mine copper smelting plant in China. The first batch of electrolytic copper products produced by the second phase electrolysis project of Tongling Nonferrous Metal Crown Copper Branch "Austrian Furnace Transformation Project" have been successfully put off the line. The design capacity is a project with an annual production capacity of 140000 tons of cathode copper, which will bring 60, 000 tons of copper to the enterprise in the year when it is put into production. After reaching the standard, the annual output of cathode copper of Jinguan Copper Branch will reach 640000 tons, making it the largest single copper smelter in the country.

SMM Network News: recently, Tongling Nonferrous Gold Crown Copper Branch "Austrian Furnace Transformation Project" Phase II electrolysis project production of the first batch of electrolytic copper products smoothly off the line. The design capacity is a project with an annual production capacity of 140000 tons of cathode copper, which will bring 60, 000 tons of copper to the enterprise in the year when it is put into production. After reaching the standard, the annual output of cathode copper of Jinguan Copper Branch will reach 640000 tons, making it the largest single copper smelter in the country.

The second phase of the electrolysis project of "Austrian Furnace Transformation Project" officially started construction on June 5, 2019, with a total investment of 209 million yuan. In the course of the construction of the project, the "one plant and four parties" participated in overcoming various difficulties such as insufficient personnel, blocked logistics and shortage of materials during the epidemic, and realized the completion of the main project in April 2020. it has set a new record for the completion of a 100000-ton electrolysis workshop in 10 months, and the construction of the project is six months ahead of the normal construction period and two months ahead of the group's plan.

On May 27, eight groups of cathode and anode plates in the second stage electrolysis were successfully completed ahead of schedule. In the early morning of June 9, the first batch of 2 groups of 36-slot electric copper went off the line smoothly. According to the person in charge of the Austrian furnace electrolysis workshop, after the cycle is stable, the daily copper output of two groups will be maintained.

The relevant person in charge of Tongling Nonferrous Group said at the ceremony of the first batch of electric copper production line that the construction of the second phase of the electrolysis project of the "Olympic Furnace Transformation Project" has fully achieved the expected goals, marking the completion of a new copper smelting industry upgrading base in Tongling Nonferrous Metals. Another solid step has been taken towards the goal of "building a model factory for copper smelting in the world".

"Click to participate in the second China (Yingtan) Copper Industry Summit Forum and the 15th China International Copper Industry chain Summit"

Scan the code to sign up for the summit or apply to join the SMM industry exchange group:

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM‘s internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or to learn more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Sinomine Resource Group Signed Cooperation Agreement with Peru's Jinda Mining for La Joya Copper Mine
1 hour ago
Sinomine Resource Group Signed Cooperation Agreement with Peru's Jinda Mining for La Joya Copper Mine
Read More
Sinomine Resource Group Signed Cooperation Agreement with Peru's Jinda Mining for La Joya Copper Mine
Sinomine Resource Group Signed Cooperation Agreement with Peru's Jinda Mining for La Joya Copper Mine
On May 20, Sinomine Resource Group Co., Ltd. and Peru Kingda Mining Co., Ltd. signed a cooperation agreement at Sinomine Resource Group's headquarters on the La Haya copper mine project. Under the agreement, Peru Kingda Mining will re-register the mining rights of the La Haya copper mine located in Peru under a joint venture jointly established by both parties and controlled by Sinomine Resource Group. Sinomine Resource Group will provide funding, technology, and industry chain resource support to jointly advance the development of this copper ore resource. In the initial phase, the project will carry out Phase I exploration work, with drilling advancing simultaneously.
1 hour ago
Tongguan Kuangjian Won the Bid for the Cuia-Mavoio Copper Mine Project in Angola, with a Bid Amount of Approximately $230 Million
1 hour ago
Tongguan Kuangjian Won the Bid for the Cuia-Mavoio Copper Mine Project in Angola, with a Bid Amount of Approximately $230 Million
Read More
Tongguan Kuangjian Won the Bid for the Cuia-Mavoio Copper Mine Project in Angola, with a Bid Amount of Approximately $230 Million
Tongguan Kuangjian Won the Bid for the Cuia-Mavoio Copper Mine Project in Angola, with a Bid Amount of Approximately $230 Million
Tongguan Mine Construction announced that it recently received a bid-winning notification from Xingyao Icarus Limited, winning the bid for the mine construction and mining engineering of the Cuia-Mavoio copper mine in Uíge Province, Angola, with a contract value of approximately $230 million. The infrastructure construction period is 18 months, and the production period is 60 months. Regarding the project background, the Cuia-Mavoio copper mine is located in Uíge Province, Angola, approximately 300 kilometers from Luanda, and includes both open-pit and underground mining. According to information previously released by Angola's Secretary of State for Mineral Resources, the project has a total investment of $250 million, with $205 million in committed funding already secured, covering two exploration license areas (approximately 3,000 square kilometers and 7,000 square kilometers, respectively). Exploration began in 2010, with the first production phase targeting open-pit ore processing of 2,500 mt per day and a total mining capacity of 4,000 mt/day; the underground mine plans to commence in H2 2026.
1 hour ago
Chilean Court Revoked $3.2 Billion Project Permit for Collahuasi Copper Mine
1 hour ago
Chilean Court Revoked $3.2 Billion Project Permit for Collahuasi Copper Mine
Read More
Chilean Court Revoked $3.2 Billion Project Permit for Collahuasi Copper Mine
Chilean Court Revoked $3.2 Billion Project Permit for Collahuasi Copper Mine
Chile's Second Environmental Court recently revoked the environmental permit for the "Infrastructure and Capacity Enhancement" project at Collahuasi, one of the world's largest copper mines. The project planned to invest over $3.2 billion, with the core objective of building a seawater desalination plant to extend the mine's lifespan. The court ruled that the mining company had failed to adequately consult with affected indigenous communities and that the assessment of environmental impacts on the marine environment was insufficient. The mining company stated that existing water sources could support short-term production and would not immediately affect production.
1 hour ago
The new project is put into production! Tongling Nonferrous will build the largest single Mine Copper smelting Plant in China - Shanghai Metals Market (SMM)