Overseas Magnesium Resource Development Accelerates; Local Supply in Europe and the US Expected to Fill the Gap [SMM Survey]

Published: Jul 2, 2026 13:35
[SMM Magnesium Survey: Ex-China Magnesium Resource Development Accelerates, US and European Local Supply Expected to Fill Gap] Australia’s Latrobe fly ash magnesium extraction demonstration plant is 33% complete, with all capacity locked in for the US market, and plans to produce magnesium in H2 2026, filling the gap of no primary magnesium in the US; Canada’s Greenland has received C$7 million in funding to advance brine-based magnesium extraction tests at a molybdenum mine in Greenland, has obtained a magnesium mining permit, and is expanding magnesium resource supply for Europe and the US.

Latrobe Magnesium’s Victoria fly ash magnesium extraction project is gaining steady momentum: construction of the world’s first hydrometallurgical demonstration plant is 33% complete, with 100% of its capacity locked in for the US market

Overall construction of Latrobe Magnesium’s Phase 1 demonstration plant in Victoria has reached 33% completion. Core works including the reduction furnace platform, briquetting screw feeder, and quicklime system have been finished, and programming integration with Rockwell Automation for the briquetting system has commenced. The project is progressing according to plan, with a second reduction furnace prototype test scheduled for mid-July, paving the way for first magnesium production in H2 2026. The demonstration plant has an annual capacity of 1,000 mt, while the Phase 2 commercial plant will produce 10 kt per year. All output has been committed to the US market via a distribution agreement with US Metal Exchange, which made a $2 million upfront payment in March. The US currently has no primary magnesium production and relies on China for about 90% of its supply. This project uses patented technology to extract magnesium from fly ash, turning waste residue from lignite power generation into high-value magnesium products, and holds dual strategic significance in supply chain substitution and waste resource utilization.

Greenland Resources receives Canadian funding to advance Greenland brine magnesium extraction project

On June 29, Greenland Resources Inc announced that it had received C$7 million (approximately $5 million) in non-repayable funding from the Canadian government for metallurgical testing at its Malmbjerg project in Greenland. The project is a molybdenum mine, with magnesium and rare earth elements as by-products. It uses approximately 35,000 m³ of brine containing around 900 ppm magnesium daily, and is studying innovative technologies to extract magnesium from the brine, while also evaluating the potential to recover magnesium from the ore body and brine. The project has already obtained a mining license for magnesium, and metallurgical testing is expected to continue until March 2028.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
[SMM Analysis] Long-Term Contracts Fail to Reverse Weak Fundamentals; Manganese Sulfate Prices to Remain Soft
Jun 30, 2026 14:32
[SMM Analysis] Long-Term Contracts Fail to Reverse Weak Fundamentals; Manganese Sulfate Prices to Remain Soft
Read More
[SMM Analysis] Long-Term Contracts Fail to Reverse Weak Fundamentals; Manganese Sulfate Prices to Remain Soft
[SMM Analysis] Long-Term Contracts Fail to Reverse Weak Fundamentals; Manganese Sulfate Prices to Remain Soft
Battery-grade manganese sulfate entered its demand off-season in May and June 2026, posting mild downward price corrections with limited downside and no sharp slumps in sight.Driven by preferential export tax rebate policies for ternary batteries in early H1, downstream manufacturers advanced export orders in bulk, creating a temporary tight supply situation......
Jun 30, 2026 14:32
"Electrolytic Manganese Faces Price Constraints Amid Loose Supply, Weak Demand, and Raw Material Substitution"
Jun 30, 2026 14:30
"Electrolytic Manganese Faces Price Constraints Amid Loose Supply, Weak Demand, and Raw Material Substitution"
Read More
"Electrolytic Manganese Faces Price Constraints Amid Loose Supply, Weak Demand, and Raw Material Substitution"
"Electrolytic Manganese Faces Price Constraints Amid Loose Supply, Weak Demand, and Raw Material Substitution"
Electrolytic manganese entered its traditional off-season in May and June 2026, with the market witnessing a loose supply-demand surplus and narrow price fluctuation ranges. Hit by sluggish downstream purchases, prices once corrected notably......
Jun 30, 2026 14:30
[SMM Analysis] May Magnesium Exports Down 4% MoM, Q2 Market Under Pressure Amid Geopolitical Risks
Jun 25, 2026 18:24
[SMM Analysis] May Magnesium Exports Down 4% MoM, Q2 Market Under Pressure Amid Geopolitical Risks
Read More
[SMM Analysis] May Magnesium Exports Down 4% MoM, Q2 Market Under Pressure Amid Geopolitical Risks
[SMM Analysis] May Magnesium Exports Down 4% MoM, Q2 Market Under Pressure Amid Geopolitical Risks
In May, China's magnesium product exports fell 4% MoM to 37.6kt. Magnesium ingot exports rose 13.7% MoM on auto and aluminum demand, while magnesium powder and alloy dropped 31.3% and 22.5% due to weak overseas demand. Japan's Jan-May imports surged 76.6% YoY, likely front-loaded, with downside risks in H2. Full-year exports are still expected to see modest growth despite headwinds from freight costs and maintenance shutdowns.
Jun 25, 2026 18:24
Register to Continue Reading
Gain access to the latest insights in metals and new energy
Already have an account?Sign in here