Sigma Lithium expects Phase 2 expansion to be operational within 12 months

Опубликовано: Nov 23, 2024 00:14
Источник: SMM
On 15 November, Sigma Lithium released its Q3 2024 results, reporting higher-than-expected production while progressing on its Phase 2 expansion project.

On 15 November, Sigma Lithium released its Q3 2024 results, reporting higher-than-expected production while progressing on its Phase 2 expansion project.

The company produced 60,237 tonnes of spodumene concentrate in Q3, exceeding its guidance of 60,000 tonnes. Sales volumes rose 9% quarter-on-quarter to 57,483 tonnes. The company said its cash unit operating costs remained among the industry’s lowest at US$513 per tonne CIF China.

The CEO Ana Cabral said the "trader-distributor" strategy allowed Sigma to secure sales above benchmark prices, reaching US$820-$920 per tonne during seasonal lows. Sigma also optimized its trade finance lines, reducing interest costs to 9.0% in Q3 from 15.5% in late 2023, and expanded access to over US$100 million in export credit lines.

Construction of the Phase 2 Greentech Plant, which will add 250,000 tonnes of annual production capacity, advanced during the quarter, supported by a US$90 million loan agreement with Brazil’s development bank, BNDES. The plant is expected to be operational within 12 months.

Заявление об источниках данных: За исключением общедоступной информации, все остальные данные обрабатываются SMM на основе общедоступной информации, рыночного общения и с опорой на внутреннюю базу данных и модели SMM. Они приведены только для справки и не являются рекомендациями для принятия решений.

По любым вопросам или для получения дополнительной информации, пожалуйста, свяжитесь: lemonzhao@smm.cn
Для получения дополнительной информации о доступе к нашим исследовательским отчётам обращайтесь:service.en@smm.cn
Sigma Lithium expects Phase 2 expansion to be operational within 12 months - Shanghai Metals Market (SMM)