Qiya Group's 2.6m kW Wind Power Project Enters Turbine Hoisting Stage in Xinjiang

Publicado: May 25, 2025 21:43

"When the wind speed is less than 3 meters per second, blade installation can commence..." In April, at the Laojunmiao North Wind Power Planning Area in Mulei Kazak Autonomous County, Xinjiang, the author learned from Xinjiang Qiya New Energy Co., Ltd. that the 2.6 million kW wind power project (Section A) of Qiya Group's 3 million kW energy storage integration project has reached a critical milestone—construction has officially entered the stage of wind turbine hoisting.

This marks the successful completion of the preliminary construction and pouring phases of Qiya Group's new energy project's wind power generation, officially entering the peak period of substantive construction, laying a solid foundation for the full grid connection and operation of 112 wind turbines in this section by the end of this year.

Declaração sobre a Fonte de Dados: Com exceção das informações publicamente disponíveis, todos os demais dados são processados pela SMM com base em informações publicamente disponíveis, comunicação de mercado e com base no modelo de base de dados interna da SMM. São apenas para referência e não constituem recomendações para a tomada de decisão.

Para quaisquer perguntas ou para obter mais informações, entre em contato: lemonzhao@smm.cn
Para mais informações sobre como aceder aos nossos relatórios de investigação, entre em contato:service.en@smm.cn
"When the wind speed is less than 3 meters per second, blade installat - Shanghai Metals Market (SMM)