Based on the initial capacity replacement plan, the past few years were expected to be a peak period for blast furnace capacity replacement

Based on the initial capacity replacement plan, the past few years were expected to be a peak period for blast furnace capacity replacement. However, with the shrinking downstream demand, the steel industry is now facing oversupply, and the struggling profits of steel mills have led to delays or cancellations of some capacity replacement projects. The steel industry's winter in 2023 is no exception. According to SMM's data on blast furnace production and shutdowns in 2023, 19 blast furnaces have been put into operation, with 2 more planned to start operating before the end of the year, totaling 33.04 million mt of capacity, which only completes 36.94% of the planned capacity. In addition, 29 blast furnaces have been shut down, with 2 more planned to shut down after the new blast furnaces start operating at the end of the year, totaling 23.75 million mt of capacity that has completed 31.2% of the shutdown plan.

Based on the timeline of production and shutdown capacity for the whole of 2023, the specific situation is as follows:

According to the tracking data from SMM on blast furnace capacity replacement progress, 21 new blast furnaces were put into operation in 2023, with a total capacity of 33.04 million mt. The phased-out capacity amounted to 23.75 million mt, resulting in a net increase of 9.29 million mt. Compared to the net increase of 5.71 million mt in 2022, there was a decrease in the net increase for 2023. Some capacity has already been phased out or even dismantled in the previous two years. Considering the current downturn in the steel industry demand and the consecutive two years of poor profitability for steel mills, the number of newly commissioned blast furnaces has been relatively slow. It is expected that the number of newly commissioned blast furnaces in 2024 will still fall short of expectations. SMM will closely monitor the actual commissioning capacity of blast furnaces in China in 2024 in real-time.

Declaração sobre a Fonte de Dados: Com exceção das informações publicamente disponíveis, todos os demais dados são processados pela SMM com base em informações publicamente disponíveis, comunicação de mercado e com base no modelo de base de dados interna da SMM. São apenas para referência e não constituem recomendações para a tomada de decisão.

Para quaisquer perguntas ou para obter mais informações, entre em contato: lemonzhao@smm.cn
Para mais informações sobre como aceder aos nossos relatórios de investigação, entre em contato:service.en@smm.cn