Anhui Province plans three aluminum processing projects in 2019 with a total capacity of 280000 tons

Publicado: Jun 19, 2019 20:18 (GMT+8)
SMM6, June 19: SMM June 19: recently, the General Office of the Provincial Government recently issued the "2019 Provincial Major Prophase work Project Promotion Plan" notice, of which there are 3 projects involving aluminum processing.

SMM6, 19 March: recently, the General Office of the Provincial Government recently issued a notice on the Promotion Plan of the Provincial Major Prophase work Project in 2019. According to the Promotion Plan, there are a total of 103 major Prophase work projects in 2019, with a total investment of 512.579 billion yuan. Of these, 19 were approved, approved or put on record by the state, with a total investment of 174.361 billion yuan, and 84 were approved, approved or put on record within the province, with a total investment of 338.218 billion yuan. Among them, there are three projects related to aluminum processing, which are arranged as follows:

Major Prophase work projects in Anhui Province in 2019 involve Aluminum processing projects

Source: general Office of the people's Government of Anhui Province, SMM

According to SMM research, Anhui Liming New Materials Company has an annual production capacity of about 20, 000 tons of aluminum foil, while Anhui Zhongwang aluminum alloy formwork and aluminum alloy car body manufacturing project is still under planning, the three projects are expected to use an annual aluminum capacity of about 280000 tons. The northern part of Anhui Province is close to Shandong and Henan, two major provinces of electrolytic aluminum supply, and adjacent to Jiangsu, Zhejiang and Shanghai in the east. Compared with Jiangsu and other places, Anhui has certain cost advantages in land price and manpower, and convenient transportation. It is an ideal area for the development of aluminum processing industry.

(SMM Shanghai Nonferrous net Liang Xuan 021 5166 6922)

Declaração sobre a Fonte de Dados: Com exceção das informações publicamente disponíveis, todos os demais dados são processados pela SMM com base em informações publicamente disponíveis, comunicação de mercado e com base no modelo de base de dados interna da SMM. São apenas para referência e não constituem recomendações para a tomada de decisão.

Para quaisquer perguntas ou para obter mais informações, entre em contato: lemonzhao@smm.cn
Para mais informações sobre como aceder aos nossos relatórios de investigação, entre em contato:service.en@smm.cn
Notícias Relacionadas
[SMM Notícias rápidas] South32 revisou a oferta de prêmio CIF MJP do 4º trimestre de 2026 para US$ 265/t
há 10 horas
[SMM Notícias rápidas] South32 revisou a oferta de prêmio CIF MJP do 4º trimestre de 2026 para US$ 265/t
Leia mais
[SMM Notícias rápidas] South32 revisou a oferta de prêmio CIF MJP do 4º trimestre de 2026 para US$ 265/t
[SMM Notícias rápidas] South32 revisou a oferta de prêmio CIF MJP do 4º trimestre de 2026 para US$ 265/t
Fontes do mercado informam: South32 revisou a oferta de prêmio CIF MJP para o 4º trimestre de 2026 para US$ 265/t, abaixo dos US$ 325/t. Validade até 5 de outubro de 2026.
há 10 horas
Índia ADC 12 se mantém firme enquanto o alumínio da LME cai; oferta restrita de sucata limita queda
01 Oct 2026 17:48 (GMT+8)
Índia ADC 12 se mantém firme enquanto o alumínio da LME cai; oferta restrita de sucata limita queda
Leia mais
Índia ADC 12 se mantém firme enquanto o alumínio da LME cai; oferta restrita de sucata limita queda
Índia ADC 12 se mantém firme enquanto o alumínio da LME cai; oferta restrita de sucata limita queda
Os preços do ADC 12 na Índia permaneceram relativamente resilientes, apesar de uma queda de 1,2% nos preços do alumínio LME de 3 meses entre 24 e 30 de setembro.
01 Oct 2026 17:48 (GMT+8)
Rio Tinto garante operações da fundição de Bell Bay até o final de 2031
01 Oct 2026 17:09 (GMT+8)
Rio Tinto garante operações da fundição de Bell Bay até o final de 2031
Leia mais
Rio Tinto garante operações da fundição de Bell Bay até o final de 2031
Rio Tinto garante operações da fundição de Bell Bay até o final de 2031
A Rio Tinto anunciou em 1º de outubro que havia chegado a acordos com o Governo da Tasmânia, o Governo da Comunidade Australiana e a Hydro Tasmania para estender o fornecimento de eletricidade à fundição de alumínio de Bell Bay até o final de 2031. Os dois governos também fornecerão um pacote de apoio combinado de A$ 200 milhões ao longo de cinco anos, contribuindo com A$ 100 milhões cada. Os termos comerciais do acordo de energia não foram divulgados. Bell Bay produz cerca de 190.000 toneladas de alumínio primário por ano, enquanto seu contrato de eletricidade existente expiraria no final de 2026. O acordo elimina a incerteza operacional imediata da fundição. Bell Bay é a terceira grande fundição de alumínio australiana a receber apoio governamental em 2026, após Boyne e Tomago, destacando a pressão contínua dos altos custos de eletricidade e da concorrência internacional.
01 Oct 2026 17:09 (GMT+8)