Analysis of production cuts in winter season 2018-2019

Publicado: Aug 03, 2018 19:37 (GMT+8)
Chinese authorities are mulling details of production cuts in the ferrous and non-ferrous industries

SHANGHAI, Aug 3 (SMM) – Chinese authorities are mulling details of production cuts in the ferrous and non-ferrous industry across the smog-prone Beijing-Tianjin-Hebei region and nearby areas, during the upcoming winter season, SMM learned from market talk this week. The cuts are part of an effort to reduce smog and improve air quality, and are stricter than cuts last winter.

Compared to last year, SMM finds major differences as follows:

Steel mills across six key cities, Tianjin, Shijiazhuang, Tangshan, Handan, Xingtai and Anyang, will be required to cut capacity by half during the heating season from November 15, 2018 to March 15, 2019. Tianjin and Xingtai are new additions to the list this year. Mills in the remaining cities in the region will need to shut no less than 30%.

Cuts are determined from the designed capacity of blast furnaces. Captive facilities including sintering machines and coke ovens will also undertake cuts or suspensions, which were not required in the previous year’s plan.

This year's plan will allow mills with pollutant emissions, across production and transportation processes, that meet the ultra-low standards to be free from the staggered production model, though SMM believes that only two mills meet these standards currently. A cut of 50% would be still imposed on these mills when pollution exceeds the orange-alert level.

Coking duration at all coke plants across the regions will be required to be extended beyond 36 hours during that period. Plants can avoid staggered production if their coke ovens have a hood, if they have installed desulphurisation and denitrification facilities and the emissions are lower than the ultra-low standards.

Casting and smelting facilities in the casting industry will be suspended. This excludes natural gas furnaces and electric furnaces with emissions that meet the targets. Such suspension can be exempted if a plant obtains approval from the local government. Natural gas furnaces and electric furnaces should still cease operation if pollution exceeds the yellow-alert level.

In terms of the impact to demand-side issues such as trucking restrictions, the latest proposal for this year looks slightly harsher than last winter for restrictions on days of heavy pollution, though outside of the heavily polluted days the number of exemptions for industries which meet certain standards, namely their power source and emissions, appears to be greater than last year. The policies aim for a 5% improvement in PM2.5 levels and a 5% reduction of the number of heavily polluted days. This suggests that demand restrictions will have to be as strict as last year, or greater. 

Details:

Action Plan on Comprehensive Control for Autumn and Winter Air Pollution in Beijing-Tianjin-Hebei and Nearby Areas

 

2017

2018

 

Date

October 1, 2017 – March 31, 2018

October 1, 2018 – March 31, 2019

Note

Days

182

182

 

Geographic coverage

Beijing, Tianjin, and 26 cities in Hebei, Shanxi, Shandong, and Henan provinces including Shijiazhuang, Tangshan, Langfang, Baoding, etc.

Beijing, Tianjin, and 26 cities in Hebei, Shanxi, Shandong, and Henan provinces including Shijiazhuang, Tangshan, Langfang, Baoding, etc.

 

Basis

Thoroughly rectify heavy pollutant companies, reduce their emissions and use of coal, highlight staggered production plans, and strengthen governmental supervision to address heavy air pollution.

 

With the industry structure, energy, transport, and land as a foundation, promote clean energy and rectification of heavy pollutant companies, overhaul bulk freight transport from road to rail, highlight remediation on diesel trucks, industrial furnaces and emission of volatile organic compounds (VOCs), and strengthen governmental supervision to address heavy air pollution.

 

Targets

  • In targeted cities, average concentration of particulate matter with a diameter below 2.5 micrometres (PM2.5) will be reduced by 15% on the year.
  • The number of heavy-pollution days will be reduced by more than 15% on the year.
  • In targeted cities, average concentration of PM2.5 particulate matter will be reduced by 5% on the year.
  • The number of heavy-pollution days will be reduced by 5% on the year.

 

 

Steel industry

  • Implement a classified management system based on each plant’s emissions, and impose staggered production by the end of September 2017.
  • Steel mills in key cities such as Shijiazhuang, Tangshan, Handan, and Anyang are required to cut steel production by 50% in the heating season. The cut is based on actual production of their blast furnaces.
  • Cuts are checked through the actual power usage at plants.

 

  • Steel mills in key cities such as Tianjin, Shijiazhuang, Tangshan, Handan, Xingtai, and Anyang are required to cut steel production by 50% in the heating season.
  • Cuts for other targeted cities should be 30% or more.
  • Production of supporting sintering machines and coke ovens will also be cut accordingly.
  • Plants whose overall operations meet the ultra-low emission standards are exempt from staggered production.
  • Plants whose production meets part of the ultra-low standards will face staggered production.
  • All plants are required to cut production by 50% during heavy pollution.

 

Coking industry

  • Coking duration at coke plants in urban areas are required to be extended beyond 48 hours, and that of plants in other areas should be extended to over 36 hours.

 

  • Coking duration across all coke plants are required to be extended beyond 36 hours.
  • Coke plants with desulphurisation and denitrification facilities and emissions that meet standards are exempt from staggered production.

 

Casting industry

  • Except for electric furnaces and natural gas furnaces that meet emission standards, all other facilities are required to suspend in the heating season. In special cases, production only starts with approval from the municipal government.
  • Production of all electric furnaces and natural gas furnaces should be suspended during heavy pollution.

 

  • Except for electric furnaces and natural gas furnaces that meet emission standards, all the other casting and smelting facilities (including blast furnaces for pig iron casting) are required to suspend in the heating season. In special cases, production only starts with approval from the municipal government.
  • Production of all electric furnaces and natural gas furnaces should be suspended during heavy pollution.

 

Building materials industry

  • Increase the proportion of staggered cuts.
  • Full suspension is imposed across industries of cement, brick kiln, ceramics, glass wool, rock wool, and plaster tablet in the heating season.
  • Cement grinding plants are required to suspend in heavy pollution.

 

  • Increase the proportion of staggered cuts.
  • Except for plants in the list for staggered production (see column on the right), full suspension is imposed across industries of cement (excluding grinding plants), brick, ceramic, glass wool, rock wool, mineral wool, waterproof building materials, and plaster tablet in the heating season.
  • Glass plants are required to cut production in heavy pollution.
  • 2018: Little or no cuts are imposed on plants powered by natural gas, electricity, or power plant thermodynamic system.
  • This includes industries of casting, ceramic, brick, glass wool, plaster tablet, waterproof building materials, rock wool, and mineral wool.
  • For plants listed in the Industrial Structure Adjustment Guideline, there will be a greater cut or suspension.

 

Nonferrous metals and chemicals sector

  • Primary aluminium producers cut production by over 30%.
  • Alumina producers cut production by 30%.
  • Carbon producers whose emissions meet standards cut production by over 50%.
  • Carbon producers whose emissions did not meet standards suspended production.  
  • Melting and casting processes in the secondary metal production cut by half.
  • Pharmaceutical companies that produce active pharmaceutical ingredients (API) and pesticide companies that use organic solvents suspended production if they discharged VOCs.
  • Primary aluminium producers cut production by over 30%.
  • Alumina producers cut production by 30%.
  • Carbon producers cut production by half.
  • Melting and casting processes in the secondary metal production cut by half.
  • Pharmaceutical companies that produce active pharmaceutical ingredients (API) and pesticide companies that use organic solvents in production suspended production if they discharged VOCs.

 

Transportation beyond peak hours

  • Transport of raw materials and finished products across steel, coke, nonferrous metals, power, and chemicals should be conducted beyond peak hours.
  • Plants are highly encouraged to use freight vehicles with fewer exhaust emissions, such as those that meet the national IV and V emission standards.
  • Vehicles that meet the national IV and above emission standards are required to account for over 80% of the overall freight vehicles during the heating season.
  • During heavy pollution, delivery vehicles are banned from entering or leaving the ports across Circum-Bohai Sea region. This excludes the transportation of basic goods for daily use or special purposes.
  • Vehicles that meet the national IV and above standards will avoid the ban if they are moving foreign traded goods or international travellers.
  • Delivery vehicles, except for those that ensure production safety, are banned from entering or leaving the plants of key sectors.
  • Transport of raw materials and finished products across steel, construction materials, coke, nonferrous metals, chemicals and mining sectors should be conducted beyond peak hours.
  • Logistics distribution in urban areas, between urban areas and ports or between ports should also be conducted beyond peak hours.
  • If pollution exceeds the yellow-alert level, diesel vehicles, except for those that ensure production safety, are banned from entering or leaving the plants. This excludes the transportation of basic goods for daily use or special purposes.
  • Vehicles that meet the national V and above standards can avoid the ban if they are moving foreign traded goods or international travellers.

 

Declaração sobre a Fonte de Dados: Com exceção das informações publicamente disponíveis, todos os demais dados são processados pela SMM com base em informações publicamente disponíveis, comunicação de mercado e com base no modelo de base de dados interna da SMM. São apenas para referência e não constituem recomendações para a tomada de decisão.

Para quaisquer perguntas ou para obter mais informações, entre em contato: lemonzhao@smm.cn
Para mais informações sobre como aceder aos nossos relatórios de investigação, entre em contato:service.en@smm.cn
Notícias Relacionadas
Emerita estende a revisão final do PFS da Faixa Piritosa Ibérica Ocidental, com divulgação prevista para as próximas semanas
há 59 minutos
Emerita estende a revisão final do PFS da Faixa Piritosa Ibérica Ocidental, com divulgação prevista para as próximas semanas
Leia mais
Emerita estende a revisão final do PFS da Faixa Piritosa Ibérica Ocidental, com divulgação prevista para as próximas semanas
Emerita estende a revisão final do PFS da Faixa Piritosa Ibérica Ocidental, com divulgação prevista para as próximas semanas
Emerita Resources forneceu uma atualização sobre o Estudo de Viabilidade Preliminar (PFS) do seu projeto polimetálico Iberian Belt West, na Espanha, afirmando que o estudo está bastante avançado, mas ainda em revisão técnica final. A empresa informou que o processo de revisão foi ampliado para incluir supervisão técnica e de garantia de qualidade adicional antes da publicação. Como resultado, a Emerita agora espera que o PFS seja divulgado nas próximas semanas, em vez do prazo anteriormente indicado. O Iberian Belt West contém mineralização de cobre, zinco, chumbo, ouro e prata e é um dos principais ativos em fase de desenvolvimento da Emerita na Espanha. Espera-se que o PFS forneça detalhes atualizados sobre o plano de mina proposto, configuração do processamento, requisitos de capital, custos operacionais e economia do projeto. A Emerita afirmou que o trabalho de revisão adicional visa garantir consistência e completude entre as disciplinas técnicas que contribuem para o estudo antes de sua finalização. A empresa não anunciou uma data de publicação específica revisada, e nenhum novo dado de produção, capital ou econômico foi divulgado na atualização mais recente. A revisão estendida adia o próximo grande marco técnico do Iberian Belt West, mas a empresa continua indicando que o PFS está próximo da conclusão. Para o mercado de cobre, a importância do estudo dependerá do perfil de produção e da economia do projeto finalmente divulgados, particularmente a contribuição do cobre em relação aos outros metais pagáveis do projeto. A atenção, portanto, permanecerá voltada para o momento da divulgação do PFS e se o estudo final alterará materialmente as perspectivas de desenvolvimento do projeto.
há 59 minutos
Cascadia Intersecta 75,55 m com 1,19% de Cu no Projeto de Cobre-Ouro Carmacks
há 1 hora
Cascadia Intersecta 75,55 m com 1,19% de Cu no Projeto de Cobre-Ouro Carmacks
Leia mais
Cascadia Intersecta 75,55 m com 1,19% de Cu no Projeto de Cobre-Ouro Carmacks
Cascadia Intersecta 75,55 m com 1,19% de Cu no Projeto de Cobre-Ouro Carmacks
Cascadia Minerals relatou resultados adicionais de perfuração de seu programa de exploração de 2026 no projeto de cobre-ouro Carmacks, em Yukon, Canadá, com novas perfurações de expansão estendendo a mineralização na Zona 2000S além dos limites do Recurso Mineral existente. O furo de sondagem CD-26-058 retornou 75,55 metros com teor de 1,19% de cobre, 0,97 g/t de ouro, 10,4 g/t de prata e 335 ppm de molibdênio, equivalente a 2,18% de cobre equivalente. O intervalo incluiu 48,66 metros com teor de 1,61% de cobre, 1,39 g/t de ouro, 15,1 g/t de prata e 475 ppm de molibdênio, equivalente a 3,03% de CuEq. No mesmo furo, um intervalo de maior teor de 14,50 metros retornou 2,30% de cobre, 2,68 g/t de ouro, 29,5 g/t de prata e 1.015 ppm de molibdênio, equivalente a 5,08% de CuEq. Um segundo furo, CD-26-059, interceptou 93,99 metros com teor de 0,96% de cobre, 0,70 g/t de ouro, 4,6 g/t de prata e 919 ppm de molibdênio, equivalente a 1,94% de CuEq. Isso incluiu 63,97 metros com 1,26% de cobre, 0,96 g/t de ouro, 6,3 g/t de prata e 1.049 ppm de molibdênio, equivalente a 2,52% de CuEq. A Cascadia afirmou que os resultados mais recentes continuam a expandir a mineralização na Zona 2000S além dos limites do Recurso Mineral atual e destacam a natureza de maior teor da extensão. Os intervalos de perfuração relatados representam espessuras perfuradas, com larguras verdadeiras estimadas em aproximadamente 60–70%. Os resultados mais recentes de expansão indicam que a mineralização de cobre-ouro na Zona 2000S se estende além dos limites do atual Recurso Mineral de Carmacks. Os intervalos amplos e as zonas internas de maior teor poderiam apoiar uma futura expansão do recurso se perfurações adicionais confirmarem a continuidade. No entanto, as novas interseções ainda não foram incorporadas a uma Estimativa de Recurso Mineral atualizada, o que significa que seu impacto final na escala do projeto e no planejamento da mina ainda está por ser determinado.
há 1 hora
NexMetals aumenta recurso de Selebi Main em 72% no Botsuana
há 1 hora
NexMetals aumenta recurso de Selebi Main em 72% no Botsuana
Leia mais
NexMetals aumenta recurso de Selebi Main em 72% no Botsuana
NexMetals aumenta recurso de Selebi Main em 72% no Botsuana
NexMetals Mining relatou um aumento de 72% na Estimativa de Recursos Minerais do depósito de cobre-níquel Selebi Main, em Botsuana, com o recurso atualizado contendo agora aproximadamente 495.400 t de cobre. A Estimativa de Recursos Minerais de Selebi Main de 2026 totaliza 32,47 milhões de t na categoria Inferida, com teor de 1,53% de cobre, 0,98% de níquel e 0,05% de cobalto. Isso se compara a 18,89 milhões de t com teor de 1,69% de cobre e 0,88% de níquel na estimativa de 2024 da empresa. O cobre contido aumentou 55%, para 495.400 t, ante 319.200 t na estimativa anterior, enquanto o níquel contido aumentou 91%, para 316.800 t, ante 165.500 t. O cobalto também foi incluído pela primeira vez na estimativa de recursos de Selebi Main, com aproximadamente 16.200 t de cobalto contido relatadas. A NexMetals afirmou que 91% do aumento na tonelagem de recursos foi atribuível a novas perfurações na Zona de Flexura. A estimativa atualizada incorpora perfurações concluídas pela NexMetals juntamente com perfurações históricas da operadora anterior BCL Limited. A empresa disse que perfurações de expansão recentes, concluídas após a data de corte dos recursos, intersectaram mineralização maciça de sulfeto adicional, o que significa que esses resultados não estão incluídos na estimativa atual. A Estimativa de Recursos Minerais atualizada para o depósito separado de Selebi North ainda está em andamento e será relatada separadamente após a conclusão. A NexMetals disse que as duas estimativas fornecerão uma visão mais abrangente da escala das Minas de Selebi mais amplas assim que a atualização de Selebi North for finalizada. O aumento de 72% na tonelagem de recursos de Selebi Main expande materialmente a escala da base de recursos de cobre-níquel da NexMetals em Botsuana, enquanto o aumento de 55% no cobre contido fortalece a relevância potencial do projeto para o futuro fornecimento regional de cobre. No entanto, toda a estimativa atualizada de recursos de Selebi Main permanece classificada como Inferida, o que significa que mais perfurações e trabalhos técnicos serão necessários antes que sua viabilidade econômica possa ser estabelecida. A atenção agora se voltará para a atualização pendente dos recursos de Selebi North e para os estudos técnicos subsequentes que abrangem as Minas de Selebi mais amplas.
há 1 hora