SHANGHAI, Sept. 23 (SMM) - Zijin Mining entered trial production of its 3.3 million-tpy lead and zinc ore processing project in Inner Mongolia’s Urat Rear Banner recently, bynrnews.com reports.
The project was commenced in 2009, and is scheduled for commissioning in the latter half of this year. Once operational, its daily ore processing capacity will reach 10,000 tonnes. The project’s zinc ore output will be 70,000 tpy (zinc content), with lead ore output of 10,000 tpy (lead content) and 360,000 tpy of standard sulfur.
The article is edited by SMM and is provided for information purpose only. SMM assumes no liability and does not warrant the accuracy, reliability or completeness of information contained or quoted in the article, either express or implied. SMM further disclaims any liability for losses in connection with the information contained or quoted in the article.
For news cooperation, please contact us by email: sallyzhang@smm.cn or service.en@smm.cn.
![[SMM Analysis] Preços de ADC 12 indiano recuam com cortes de preços das OEMs; Mumbai resiliente em meio à reposição festiva](https://imgqn.smm.cn/usercenter/zjiqN20251217171650.jpg)

![Custos de divergência de matérias-primas permanecem altos; fluoreto de alumínio sobe levemente em meio à concorrência intensificada [Revisão Semanal de Sal de Flúor da SMM]](https://imgqn.smm.cn/usercenter/ceevU20251217171653.jpg)