Luzhou Generation-Grid-Load-Storage Integrated Energy Project (Phase I) PV Module Procurement Second Failed Bidding

Published: Jul 7, 2026 13:30
On July 2, the tender failure announcement for the PV module procurement (the second tender) of the Luzhou Generation-Grid-Load-Storage Integrated Energy Project (Phase I) was released. The announcement disclosed that the second tender was opened on June 30, 2026. As fewer than three bidders submitted the bid security, this tender failed. The section will be re-tendered in accordance with regulations. Previously, when this section was opened on May 22, 2026, it also failed because fewer than three bidders submitted bids.

On July 2, the failed-bid announcement for the PV module procurement (the second tender) of the Luzhou Generation-Grid-Load-Storage Integrated Energy Project (Phase I) was released.

The announcement disclosed that the second tender was opened on June 30, 2026, and because fewer than three entities paid the bid bonds, this tender failed, and this section will be re-tendered as per regulations.

Previously, when this section was opened on May 22, 2026, it also failed because fewer than three bidders participated.

The tender information shows that the procuring entity for this project is Luzhou Smart Integrated Energy Co., Ltd., with a project budget of no more than 850,000 yuan (tax inclusive). The project is expected to construct a distributed PV power generation system with a total installed capacity of approximately DC side 29.83MWp29.83m4p and AC side 23.851m, and an ESS power station with a total capacity of 8IV/16mwh. It involves the Intelligent Terminal Industrial Park in Luzhou High-tech Zone, the plant area of Luzhou Changjiang Machinery Co., Ltd., and the plant area of Luzhou Haoneng Transmission Technology Co., Ltd., with a total of 29 buildings. The specific project details are as follows: 1. Construction of approximately DC side 3.79m4p/AC side 3.10M distributed PV power station in Zone C of Standardized Plants, Intelligent Terminal Industrial Park, Jiangyang District, Luzhou; 2. Construction of approximately DC side 2.03p/AC side 1.501 distributed PV power station in Zone D of Standardized Plants, Intelligent Terminal Industrial Park, Jiangyang District, Luzhou; 3. Construction of approximately DC side 1.7514p/AC side 1.40MW distributed PV power station in the Shouyun self-built plant area of Intelligent Terminal Industrial Park, Jiangyang District, Luzhou; 4. Construction of approximately DC side 10.18p/AC side 8.10M4 distributed PV power station in the plant area of Luzhou Changjiang Machinery Co., Ltd.; 5. Construction of approximately DC side 12.084p/AC side 9.7514 distributed PV power station in the plant area of Luzhou Haoneng Transmission Technology Co., Ltd.; 6. Construction of approximately 2.5IW/5IW behind-the-meter ESS in Zone A of Standardized Plants, Intelligent Terminal Industrial Park, Jiangyang District, Luzhou; 7. Construction of approximately 2.51W/5IW behind-the-meter ESS in Zone B of Standardized Plants, Intelligent Terminal Industrial Park, Jiangyang District, Luzhou; 8. Construction of approximately 3mw/6mwh behind-the-meter ESS in Zone C of Standardized Plants, Intelligent Terminal Industrial Park, Jiangyang District, Luzhou.

The selected contractor should provide the entire process of preparing the grid connection plan for the PV power generation system and ESS power station for this project, specifically including but not limited to:

(1) Conduct site surveys and data collection;

(2) Prepare the grid connection plan for the PV power generation system (including 29.83MWp/23.85MW distributed PV);

(3) Prepare the grid connection plan for the ESS power station (including the 8MW/16MWh ESS);

(4) Complete the grid connection system design;

(5) Complete the technical and economic feasibility study of the grid connection plan;

(6) Collaborate with State Grid Sichuan Electric Power Company Luzhou Power Supply Company to complete the review, modification, and optimization of the grid connection plan;

(7) Obtain the official grid connection plan document from State Grid Sichuan Electric Power Company Luzhou Power Supply Company (sealed version by State Grid Sichuan Electric Power Company Luzhou Power Supply Company);

(8) Provide technical consulting services during the plan preparation process;

(9) Complete other related work required by the procuring entity.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
ADC12 prices generally stable with slight rise, domestic-overseas inversion continues to repair [ADC12 Price Daily Review]
Common.Time.hoursAgo
ADC12 prices generally stable with slight rise, domestic-overseas inversion continues to repair [ADC12 Price Daily Review]
Read More
ADC12 prices generally stable with slight rise, domestic-overseas inversion continues to repair [ADC12 Price Daily Review]
ADC12 prices generally stable with slight rise, domestic-overseas inversion continues to repair [ADC12 Price Daily Review]
[ADC12 Price Daily: ADC12 Prices Generally Stable with Slight Rise, Inverted Domestic-Overseas Spread Continues to Narrow] Quotes in the secondary aluminum alloy market predominantly held steady with a slight rise today. The SMM ADC12 price increased by 50 yuan/mt from the previous trading day to 24,050 yuan/mt. The rebound in aluminum prices and high cost-side operations remained key factors supporting enterprise quotes. Tight supply of aluminum scrap and persistently high procurement costs kept enterprises' willingness to cut prices low.
Common.Time.hoursAgo
[SMM Analysis] South Africa's Chrome Ore and High-Carbon Ferrochrome Exports
Jul 6, 2026 17:12
[SMM Analysis] South Africa's Chrome Ore and High-Carbon Ferrochrome Exports
Read More
[SMM Analysis] South Africa's Chrome Ore and High-Carbon Ferrochrome Exports
[SMM Analysis] South Africa's Chrome Ore and High-Carbon Ferrochrome Exports
South Africa's global chrome ore exports eased marginally in May 2026 to 2.43 million mt, down 1.82% month-on-month from 2.47 million mt in April, but still 43.08% higher than a year earlier. High-carbon ferrochrome (HC FeCr) exports moved in the opposite direction, rising 5.66% MoM to 123,795 mt, though volumes remained 48.76% below May 2025.
Jul 6, 2026 17:12
[SMM Analysis] H1 2026 China Rhenium Market Semi-Annual Review
Jul 6, 2026 15:05
[SMM Analysis] H1 2026 China Rhenium Market Semi-Annual Review
Read More
[SMM Analysis] H1 2026 China Rhenium Market Semi-Annual Review
[SMM Analysis] H1 2026 China Rhenium Market Semi-Annual Review
Jul 6, 2026 15:05
Register to Continue Reading
Gain access to the latest insights in metals and new energy
Already have an account?Sign in here
Luzhou Generation-Grid-Load-Storage Integrated Energy Project (Phase I) PV Module Procurement Second Failed Bidding - Shanghai Metals Market (SMM)