According to Electra Battery Materials on October 5, the company has appointed Garzon Duenas as General Manager and Commissioning Lead to oversee the transition of its Ontario cobalt sulfate refinery from construction into commissioning, ramp-up and commercial operations.
Electra plans to begin partial commissioning in the fourth quarter of 2026, achieve mechanical completion in the second quarter of 2027, proceed with full commissioning and ramp-up in the third quarter, and reach commercial production in the fourth quarter of 2027.
The company also said that following a planned Phase II expansion, cobalt hydroxide processing capacity could increase to approximately 22,500 tonnes per year, equivalent to about 6,500 tonnes per year of contained cobalt. Electra expects the facility to become North America’s first battery-grade cobalt sulfate refinery. The updated management structure and commissioning schedule mark another step toward commercial operation.
![Cobalt products stage a "major counteroffensive" as spot quotes collectively rebound from year-to-date lows; refined cobalt jumps 40,000 in a single week [Weekly Review]](https://imgqn.smm.cn/usercenter/MjfPv20251217171728.jpg)
![[SMM News] Chile’s lithium output to reach 335,000 mt in 2027](https://imgqn.smm.cn/usercenter/ajAmi20251217171726.jpg)
![[SMM News] GFEX to launch lithium hydroxide futures on Nov 26 and options on Nov 27](https://imgqn.smm.cn/usercenter/smDhO20251217171726.jpg)