CNMC Luanshya Advances Flooded Mine Rehabilitation, Targets September 2027 Start-up
CNMC Luanshya Copper Mines is advancing rehabilitation of its flooded mining areas in Zambia. According to an October 26 report in China Nonferrous Metals News, cumulative dewatering had reached 93.43 million cubic metres, more than 16 kilometres of shallow-level workings had been cleared and restored, and the permanent headframe at the Muliashi South shaft had been installed. The shallow project is designed to produce approximately 12,000 tonnes of copper in concentrate annually at full capacity, while the planned Shaft No. 28 deep-level project is designed to produce approximately 43,000 tonnes per year. Combined annual output would reach approximately 55,000 tonnes of copper in concentrate once both projects reach full capacity.