Magna Mining Approves Restart of Levack Nickel-Copper Mine, Targeting Mid-2028 Commercial Production

Published: Oct 09, 2026 09:24 (GMT+8)

Magna Mining has formally approved the restart of the Levack nickel-copper mine in Ontario's Sudbury Basin, which has been out of production since 2018. The company will rehabilitate existing underground infrastructure, recommission hoisting systems and accelerate underground development and surface construction over the coming months.

The new PEA outlines approximately 7.3 years of commercial production, with start-up targeted for mid-2028 and average annual payable production of around 36.8 million lb of copper equivalent. Initial capital is estimated at C$70.1 million, while Magna calculates a much lower net funding requirement after pre-commercial operating cash flow and tax credits. Early mining will prioritize higher-grade copper and precious-metals-rich footwall zones.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Florence Copper Holds Commercial Launch Ceremony as the U.S. Welcomes Its First Major New Copper Source Since 2008
25 mins ago
Florence Copper Holds Commercial Launch Ceremony as the U.S. Welcomes Its First Major New Copper Source Since 2008
Read More
Florence Copper Holds Commercial Launch Ceremony as the U.S. Welcomes Its First Major New Copper Source Since 2008
Florence Copper Holds Commercial Launch Ceremony as the U.S. Welcomes Its First Major New Copper Source Since 2008
Florence Copper, a project owned by Taseko Mines, held a commercial launch ceremony in Arizona on October 6. The project produced its first copper cathodes in February 2026, meaning the ceremony marked the formal transition to commercial operations rather than the start of initial production. Florence Copper has been described as the first major new greenfield copper source in the United States since 2008. The project uses in-situ copper recovery (ISCR) combined with solvent extraction and electrowinning (SX/EW). It has a nameplate capacity of 38,600 tonnes of LME Grade A copper cathodes per year, based on the original 85 million-pound-per-year design capacity. The mine life is expected to be around 22 years, with estimated cumulative production of approximately 680,000 tonnes of copper. The project extracts copper through injection and recovery wells rather than conventional open-pit mining. The company said Florence Copper produced nearly 3,175 tonnes of copper between February and June 2026. The operation remains in the ramp-up phase and is expected to reach full production in 2027. All cathode copper produced at the project will remain in the United States to supply domestic manufacturers and other strategic industries. The project has created more than 200 direct jobs.
25 mins ago
【Flash | Peru’s August Molybdenum Export Value Rises 33% YoY】
31 mins ago
【Flash | Peru’s August Molybdenum Export Value Rises 33% YoY】
Read More
【Flash | Peru’s August Molybdenum Export Value Rises 33% YoY】
【Flash | Peru’s August Molybdenum Export Value Rises 33% YoY】
Peru’s Central Reserve Bank reported molybdenum export value of $187 million in August 2026, down 3.6% from the revised July figure but up 32.6% year on year. January–August export value reached $1.371 billion, up 23.6% year on year. The series measures FOB export value rather than physical volume or mine production.
31 mins ago
Cochilco: 80.1% of Chilean copper mining power now accredited renewable
1 hour ago
Cochilco: 80.1% of Chilean copper mining power now accredited renewable
Read More
Cochilco: 80.1% of Chilean copper mining power now accredited renewable
Cochilco: 80.1% of Chilean copper mining power now accredited renewable
Chile's copper commission Cochilco reports that accredited renewable electricity now accounts for 80.1% of total power used by the country's copper mining industry, underscoring how far the sector has moved toward a clean-energy matrix. Cochilco notes that electricity represents roughly 30% of national demand from copper operations and up to 30% of some mines' operating costs. As ore grades decline and desalination expands, power use per tonne of copper keeps climbing, making long-term renewable PPAs central to securing both low-carbon credentials and cost control. The data reinforces Chile's position as a supplier of traceable, low-emission copper as buyers and regulators increasingly price embedded carbon.
1 hour ago