Sulphuric Acid Shortage: A Key Constraint on Zambia’s Copper Growth

Published: Sep 25, 2026 16:43 (GMT+8)
Zambia’s sulphuric acid shortage is becoming a growing constraint on copper production and refining. Jubilee Metals reported acid costs rising by more than 200% in Q4 FY2026, while Sable cathode output fell to 250 t from 361 t in Q3. Government data also showed small-scale copper production down 35.2% YoY in H1 2026, highlighting the sector’s exposure to tight acid availability and higher processing costs.

━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━━

SMM ANALYSIS  |  AFRICA COPPER

Sulphuric Acid Shortage Emerges as a Constraint on Zambia’s Copper Growth

Tight domestic acid availability is already showing up in policy action, small-scale mining weakness and refinery cost pressure, with Jubilee Metals reporting a more than 200% increase in acid costs during Q4 FY2026.

25 September 2026  |  SMM Analysis

>200%

Q4 FY2026 acid cost increase

Jubilee Metals

250 t

Sable Q4 cathode output

down from 361 t in Q3

-35.2%

Small-scale copper production

Zambia H1 2026 YoY

~1.1 Mt

Kansanshi acid output

2025 production

 

Zambia’s copper sector is expanding investment and processing capacity, but sulphuric acid availability is becoming a visible constraint for parts of the domestic value chain. Ministry of Mines data show national copper production rising only 0.45% year on year to 447,181 t in H1 2026, while small-scale copper production fell 35.2%. The Ministry attributed the small-scale decline partly to inadequate domestic sulphuric acid supply and the delayed end of the rainy season.

Recent company disclosures add a more immediate operating signal. Jubilee Metals reported that domestic acid availability in Zambia reduced significantly during Q4 FY2026, with acid costs rising by more than 200% and diesel costs increasing by 90%. The company said these conditions had a marked impact on production at its Sable Refinery and contributed to temporary closures among some metal processors in its operating area.

┃ Jubilee data show pressure reaching the refining stage

Sable produced 1,207 t of copper cathode in FY2026, up 17.5% from 1,027 t in FY2025. However, the quarterly profile weakened toward year-end: cathode output rose from 217 t in Q1 to 379 t in Q2, eased to 361 t in Q3 and then fell to 250 t in Q4. Q4 production was therefore about 31% below Q3 and 34% below the Q2 peak.

The Q4 fall should not be attributed to acid alone. Jubilee also reported operational factors including extended maintenance at Roan and pre-stripping work at Molefe. The more defensible conclusion is that acid availability and cost pressure became one of several operating constraints, and one that Jubilee explicitly linked to Sable’s performance during the quarter.

┃ The constraint is uneven across Zambia’s copper producers

The impact of tight sulphuric acid supply is not uniform. Large integrated operations with captive smelting and acid production are less exposed to the merchant market than smaller leach operators and independent processors. This helps explain why national copper production still edged higher while small-scale output fell sharply.

First Quantum’s disclosures illustrate the difference. Kansanshi generated approximately 1.1 million t of sulphuric acid in 2025, almost all of which was consumed on site in leaching circuits for cathode production. Following the smelter expansion, Acid Plant 5 could generate supplementary acid for internal use or external sale, depending on mine geology and processing requirements.

This means Zambia can be a significant acid producer and still have a shortage in the merchant market. Installed acid capacity is not the same as freely available supply. Internal consumption, ore type, smelter availability, contractual allocation, transport economics and local pricing all affect how much acid reaches third-party consumers.

┃ Upstream copper units are growing faster than saleable output

Jubilee’s production mix also shows why copper growth is not only a mining issue. Combined copper units from Roan and Molefe reached 3,739 t in FY2026, up 225.0% year on year. Roan total production increased 145.5% to 2,823 t. Yet final copper products produced for sale increased only 1.3% to 2,120 t, while Sable cathode production rose 17.5%.

Part of this gap reflects the build-up of oxide concentrate fines awaiting processing through Roan’s newly commissioned dewatering circuit and the fact that Jubilee reports different streams at different stages of the value chain. Even so, the contrast highlights the broader issue: converting mined or concentrated copper units into saleable metal depends on refinery availability, reagents, energy and logistics, not only ore supply.

┃ SMM outlook

Through the remainder of 2026, sulphuric acid availability is likely to remain an important variable for Zambia’s oxide and mixed-ore copper producers. The March export-permit system may help retain more acid for domestic users, but it does not create additional supply. In the near term, the market balance will depend on smelter operating rates, internal acid consumption at integrated mines and the amount of surplus product that producers are willing and able to release into the merchant market. For smaller leach operators, delivered availability and price could therefore remain more important than Zambia’s headline installed acid capacity.

There are signs that the supply side could improve. First Quantum has said the Kansanshi smelter expansion and Acid Plant 5 provide the potential to generate supplementary sulphuric acid, depending on mine geology and internal processing requirements. The expanded smelter is configured for around 1.5 million tonnes per year of acid capacity, including Acid Plant 5 at approximately 900 tonnes per day. However, Kansanshi consumed almost all of the roughly 1.1 million tonnes it produced in 2025 on site, which means additional capacity will not automatically translate into an equivalent increase in merchant supply.

The restart of KCM’s Nchanga Smelter in September also introduces a potential source of relief. The 311,000-tonne-per-year smelter returned after a 106-day rehabilitation programme, and KCM identifies sulphuric acid as one of the products manufactured at the Nchanga complex. If the smelter and associated acid systems operate consistently, additional output could improve domestic availability. The extent of that benefit will depend on KCM’s own leach requirements, operating rates and how much acid is ultimately made available to third-party customers.

Demand for acid could rise at the same time. Jubilee expects Sable to receive feed from a growing portfolio of Jubilee-controlled sources as Molefe develops and Project G moves toward targeted development from February 2027. Higher oxide and mixed-feed throughput would increase the importance of reliable reagent supply. Unless merchant acid availability expands alongside this processing growth, the market could remain vulnerable to renewed price spikes or temporary throughput constraints even as Zambia’s mined copper base increases.

Looking ahead to 2027, the acid balance could become an increasingly important differentiator between integrated and merchant-dependent producers. A sustained improvement in smelter uptime, additional third-party acid sales and effective domestic allocation could allow smaller mines and independent processors to recover output and participate more fully in Zambia’s copper-growth cycle. If the market remains tight, however, production growth is more likely to remain concentrated among large integrated operators that can secure acid internally. Key indicators to watch will be merchant acid prices, smelter operating rates, export-permit flows, third-party acid sales and Sable’s ability to convert rising upstream feed into saleable copper products.

Sources: Jubilee Metals Group, FY2026 Production and Operational Update, 14 September 2026; Zambia Ministry of Mines and Minerals Development, H1 2026 mining-sector update; First Quantum Minerals, Q1 2026 results and Zambia operations presentation; Zambia Ministry of Commerce, Trade and Industry, Sulphuric Acid Export Permit notice; Konkola Copper Mines corporate information and ZNBC report on the September 2026 Nchanga Smelter restart; SMM calculations based on public source data.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
KGHM and South32 launch US$725m Sierra Gorda expansion, lifting copper capacity 26%
2 hours ago
KGHM and South32 launch US$725m Sierra Gorda expansion, lifting copper capacity 26%
Read More
KGHM and South32 launch US$725m Sierra Gorda expansion, lifting copper capacity 26%
KGHM and South32 launch US$725m Sierra Gorda expansion, lifting copper capacity 26%
KGHM and South32 have broken ground on a fourth grinding line at the Sierra Gorda copper-molybdenum mine in Chile's Atacama region. The US$725 million expansion runs for three years from January 2027, with completion by late 2029 and full output in H2 2030. Ore processing capacity rises 26%, from 131,000 tonnes per day to 165,000 tpd. Annual copper output is projected to climb from 165,000 tonnes in 2025 to 195,000 tonnes, with 6,000 tonnes of molybdenum, 58,000 ounces of gold and 1.7 million ounces of silver as by-products. The project creates over 900 direct jobs and is funded from operating cash flow and debt. Unit operating costs are expected to fall about 10%.
2 hours ago
Emerita Extends Final Review of Iberian Belt West PFS, Release Expected in Coming Weeks
3 hours ago
Emerita Extends Final Review of Iberian Belt West PFS, Release Expected in Coming Weeks
Read More
Emerita Extends Final Review of Iberian Belt West PFS, Release Expected in Coming Weeks
Emerita Extends Final Review of Iberian Belt West PFS, Release Expected in Coming Weeks
Emerita Resources has provided an update on the Preliminary Feasibility Study (PFS) for its Iberian Belt West polymetallic project in Spain, saying the study is well advanced but remains under final technical review.​ The company said the review process has been expanded to include additional technical and quality-assurance oversight before publication. As a result, Emerita now expects the PFS to be released in the coming weeks rather than within the previously indicated timeframe.​ Iberian Belt West hosts copper, zinc, lead, gold and silver mineralization and is one of Emerita’s principal development-stage assets in Spain. The PFS is expected to provide updated detail on the proposed mine plan, processing configuration, capital requirements, operating costs and project economics.​ Emerita said the additional review work is intended to ensure consistency and completeness across the technical disciplines contributing to the study before it is finalized.​ The company did not announce a revised specific publication date, and no new production, capital or economic figures were disclosed in the latest update.​ The extended review delays the next major technical milestone for Iberian Belt West, but the company continues to indicate that the PFS is nearing completion. For the copper market, the significance of the study will depend on the production profile and project economics ultimately disclosed, particularly the contribution of copper relative to the project’s other payable metals. Attention will therefore remain on the timing of the PFS release and whether the final study materially changes the project’s development outlook.
3 hours ago
Cascadia Intersects 75.55 m at 1.19% Cu at Carmacks Copper-Gold Project
3 hours ago
Cascadia Intersects 75.55 m at 1.19% Cu at Carmacks Copper-Gold Project
Read More
Cascadia Intersects 75.55 m at 1.19% Cu at Carmacks Copper-Gold Project
Cascadia Intersects 75.55 m at 1.19% Cu at Carmacks Copper-Gold Project
Cascadia Minerals has reported additional drill results from its 2026 exploration programme at the Carmacks copper-gold project in Yukon, Canada, with new step-out drilling extending mineralization at Zone 2000S beyond the boundaries of the existing Mineral Resource.​ Drill hole CD-26-058 returned 75.55 metres grading 1.19% copper, 0.97 g/t gold, 10.4 g/t silver and 335 ppm molybdenum, equivalent to 2.18% copper-equivalent. The interval included 48.66 metres grading 1.61% copper, 1.39 g/t gold, 15.1 g/t silver and 475 ppm molybdenum, equivalent to 3.03% CuEq.​ Within the same hole, a higher-grade interval of 14.50 metres returned 2.30% copper, 2.68 g/t gold, 29.5 g/t silver and 1,015 ppm molybdenum, equivalent to 5.08% CuEq.​ A second hole, CD-26-059, intersected 93.99 metres grading 0.96% copper, 0.70 g/t gold, 4.6 g/t silver and 919 ppm molybdenum, equivalent to 1.94% CuEq. This included 63.97 metres at 1.26% copper, 0.96 g/t gold, 6.3 g/t silver and 1,049 ppm molybdenum, equivalent to 2.52% CuEq.​ Cascadia said the latest results continue to expand mineralization at Zone 2000S beyond the limits of the current Mineral Resource and highlight the higher-grade nature of the extension. The reported drill intervals represent drilled thicknesses, with true widths estimated at approximately 60–70%.​ The latest step-out results indicate that copper-gold mineralization at Zone 2000S extends beyond the boundaries of the current Carmacks Mineral Resource. The broad intervals and higher-grade internal zones could support future resource expansion if additional drilling confirms continuity. However, the new intersections have not yet been incorporated into an updated Mineral Resource Estimate, meaning their ultimate impact on project scale and mine planning remains to be determined.
3 hours ago