Bezant Targets First Concentrate at Namibia’s Hope & Gorob in September

Published: Sep 03, 2026 21:15 (GMT+8)

Bezant Resources said development of the Hope & Gorob copper-gold project in Namibia and the associated Tsoaxaub Metals Processing Plant remains in line with the current project schedule, with first run-of-mine ore expected to be processed during September 2026. Subject to completion of the remaining commissioning activities, processing of the first ROM ore is expected to generate the project’s first concentrate. Ore from the first two mine blasts has already been stockpiled and is ready for transport to the processing plant, while Bezant said the stockpiled tonnage exceeded initial projections due to additional ore recovery recorded in the company’s Mineral Inventory.

Development work is progressing at both the mine and processing plant. Mine-site camp construction is approximately 75% complete, around 75% of surface infrastructure has been delivered and is being installed, and the full Unitrans mining and haulage fleets are now on site. At the Tsoaxaub plant, Bezant has received the C1 Civils and Structural Completion Certificate, confirming completion of major structural steelwork and civil works, while the C2 Mechanical Completion Certificate is scheduled for completion during September. Electrical drives and instrumentation are around 90% complete, with the cone crusher, flotation equipment, tailings infrastructure and other processing components undergoing final preparation ahead of commissioning.

Bezant has also accelerated its review of a Phase II expansion plan, considering current and projected copper, gold and silver prices as well as the potential inclusion of lower-grade mineralisation that had previously been considered sub-economic. The company is evaluating a higher mass-pull operating strategy for the ore sorter that could increase copper recoveries, although potentially at a lower pre-concentrate grade. Based on the current Mineral Inventory, existing JORC (2012) Mineral Resource, planned flotation-plant capacity and the higher mass-pull scenario under consideration, management believes Hope & Gorob has the potential to support an approximately 35-year mine life. Bezant has not yet published a revised economic model incorporating this longer-life scenario.

SMM Analysis: The September processing target places Hope & Gorob close to the transition from mine development into initial concentrate production, with ROM ore already stockpiled and key processing infrastructure approaching mechanical completion. The potential 35-year mine life and Phase II expansion remain under technical and economic review and should not yet be treated as a confirmed revised development plan. In the near term, the key milestone to watch will be completion of plant commissioning and confirmation of first concentrate production during September.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
What Could a Cobre Panamá Restart Mean for Global Copper Supply? [SMM Analysis]
1 hour ago
What Could a Cobre Panamá Restart Mean for Global Copper Supply? [SMM Analysis]
Read More
What Could a Cobre Panamá Restart Mean for Global Copper Supply? [SMM Analysis]
What Could a Cobre Panamá Restart Mean for Global Copper Supply? [SMM Analysis]
Cobre Panamá could again become a major source of global copper supply if Panama and First Quantum agree on a new operating framework. The mine produced 330.9 kt of copper in 2023 and historically supplied around 1% of global output. While stockpile processing has resumed, fresh mining remains suspended. Any restart would likely be phased, with timing dependent on negotiations, legal conditions and operational remobilisation.
1 hour ago
Vedanta Plans $2.3 Billion Expansion in India and Saudi Arabia, and Advances Tuticorin Smelter Restart
6 hours ago
Vedanta Plans $2.3 Billion Expansion in India and Saudi Arabia, and Advances Tuticorin Smelter Restart
Read More
Vedanta Plans $2.3 Billion Expansion in India and Saudi Arabia, and Advances Tuticorin Smelter Restart
Vedanta Plans $2.3 Billion Expansion in India and Saudi Arabia, and Advances Tuticorin Smelter Restart
Vedanta has unveiled a major investment plan, under which Vedanta Copper intends to invest $2.3 billion in India and Saudi Arabia over the next three to four years, targeting annual copper production of more than 1 million tonnes by 2030. The company aims to produce 500,000 tonnes annually in both India and Saudi Arabia, alongside existing production of 100,000 tonnes in Fujairah, UAE. Around $2 billion will be invested in Saudi copper mining, smelting and rod projects, with an investment decision on the proposed Saudi copper smelter expected this quarter. Vedanta is also seeking to restart its Tuticorin copper smelter in India, which has been closed since 2018. The company expects a court ruling within three months and, subject to approval, plans to invest $250 million in refurbishing the facility, targeting a restart within eight to nine months and annual copper output of 250,000 tonnes. Meanwhile, its Silvassa facility is operating at around 95% capacity, with annualised copper cathode production exceeding 245,000 tonnes.
6 hours ago
London BTC flags copper and antimony at Nevada Black Star
8 hours ago
London BTC flags copper and antimony at Nevada Black Star
Read More
London BTC flags copper and antimony at Nevada Black Star
London BTC flags copper and antimony at Nevada Black Star
London BTC Company Limited (LSE:BTC, OTCQB:VINZF) announced on 5 October 2026 initial on-site pXRF results from its Black Star gold-critical minerals project in Pershing County, Nevada. A maiden programme collected 69 rock-chip samples along a 2.5km corridor between the Western and Eastern targets. pXRF readings showed antimony up to 0.44% Sb, copper up to 30.0% Cu, bismuth up to 0.73% Bi and silver up to 811 ppm Ag, with the antimony-copper association appearing at both ends of the corridor. The signature mirrors a historical 1985 sample 120m south of the claims (>1% Sb, 2% Cu, 700 ppm Ag). Earlier due-diligence sampling returned up to 16.23 g/t gold and 50.5 g/t silver. Samples are now with MSALABS for laboratory assays, with full multi-element geochemistry including antimony, tungsten and copper to follow. Copper, as a by-product credit, adds strategic appeal under US critical-minerals policy, though results remain preliminary field readings.
8 hours ago