[SMM Analysis] IDB Invest to Lead Up to $700-Million Financing for Posco's Lithium Expansion in Argentina

Published: Aug 31, 2026 14:47 (GMT+8)

On August 28(th), IDB Invest, the private-sector arm of the Inter-American Development Bank, said Friday it will lead financing of up to $700-million for a Posco Holdings unit to expand lithium production at its Sal de Oro project, on the border of Salta and Catamarca provinces, Argentina. The package includes a $250-million loan from IDB Invest, with a further $450-million expected from other institutions.

Per IDB Invest's statement, the financing supports startup and phased expansion of two Posco Argentina plants one for lithium hydroxide, one for lithium carbonate expected to reach about 48,000 t/yr once fully operational, creating around 620 jobs. Figures trace to IDB Invest's statement alone; no independent corroboration from Posco or Argentine authorities.

Argentina, Chile, and Bolivia form the Lithium Triangle, holding the world's largest lithium resources.

SMM View: IDB Invest's $250 million is committed; the remaining $450-million is expected, not closed. The 48,000 t/yr figure is a design target for plants not yet built, with no timeline given.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
[SMM News] Brazil regulator orders partial halt at Sigma Lithium mine over ‘imminent risk’
1 hour ago
[SMM News] Brazil regulator orders partial halt at Sigma Lithium mine over ‘imminent risk’
Read More
[SMM News] Brazil regulator orders partial halt at Sigma Lithium mine over ‘imminent risk’
[SMM News] Brazil regulator orders partial halt at Sigma Lithium mine over ‘imminent risk’
On October 2(nd), Sigma Lithium has suspended all mining and industrial activities at its Grota do Cirilo operation in Brazil, its sole producing asset, pending a federal appeals court ruling on a preliminary injunction over its environmental licences. Brazil's national mining agency (ANM) had ordered mining halted on the eastern slope of the north pit. Concentrate output from the site is halted during the suspension, and sales of lithium fines continue. Sigma pushed back its 12-month production guidance of 240,000 mt by three months and maintains its FY2027 target of 330,000 mt of concentrate.
1 hour ago
[SMM News] Lithium Argentina outlines phased expansion plan for Cauchari-Olaroz
1 hour ago
[SMM News] Lithium Argentina outlines phased expansion plan for Cauchari-Olaroz
Read More
[SMM News] Lithium Argentina outlines phased expansion plan for Cauchari-Olaroz
[SMM News] Lithium Argentina outlines phased expansion plan for Cauchari-Olaroz
Lithium Argentina confirmed a Stage 2 expansion at the Cauchari-Olaroz salt lake project in Argentina, adding 45,000 mt/y of lithium carbonate capacity and lifting total capacity to 85,000 mt/y. Of this, an initial 10,000 mt/y module using adsorption direct lithium extraction (DLE) is expected online in 2028. This estimates after-tax NPV at $3.1 billion and IRR at 28.5% at a lithium carbonate price of $18,000/mt, with operating costs of $5,006/mt. Total investment for Stage 2 is $1 billion. The project remains subject to regulatory approvals, and detailed engineering for the initial module is due later this year. The additional supply is scheduled from 2028 onward.
1 hour ago
[SMM News] Patagonia Lithium completes 72-hour pump test at Cilon
1 hour ago
[SMM News] Patagonia Lithium completes 72-hour pump test at Cilon
Read More
[SMM News] Patagonia Lithium completes 72-hour pump test at Cilon
[SMM News] Patagonia Lithium completes 72-hour pump test at Cilon
Patagonia Lithium completed a 72-hour pump test at well eight on its Cilon concession, with a flow rate of 2,043 litres/hour and 146,800 litres extracted. Lithium concentration reached 232 ppm at 250m depth. About 34 kg of lithium was pumped, equal to 180 kg of lithium carbonate equivalent (LCE). In the 24-hour recovery test, the water level returned from 52.4m to the static level of 3.64m. The company identified an aquifer zone of interest between 226m and 324m depth and is updating its mineral resource estimate, with a scoping report to follow. The project is at the exploration stage, and no production timeline has been announced.
1 hour ago