On August 24, the Ecology and Environment Bureau of Anshun City, Guizhou Province, released the EIA acceptance public notice for the “Guanling County Zhengjie Agricultural PV Power Station Project (Change)”.
The notice showed that the Guanling County Zhengjie Agricultural PV Power Station Project is located in Gangwu Town, Guanling County, Anshun City, with a total investment of 786.78 million yuan and a construction period of 8 months. This project was resubmitted for approval due to a major change.
Previously, on November 20, 2024, the project obtained the “Reply of the Ecology and Environment Bureau of Anshun City on the Environmental Impact Report Form for the Guanling County Zhengjie Agricultural PV Power Station” (Anhuanbiao Pifu [2024] No. 147), and construction commenced in July 2025.
As of January 2026, within Plot No. 4 covered by the original EIA approval, installation of PV array mounting structures was underway (using manual drilling and drone hoisting), while construction had not started in other areas. During the land acquisition process, due to land transfer reasons, it was necessary to reduce the red-line boundary scope of the original EIA and reselect the site outside the original EIA red-line boundary; construction had not started within the land area of the reselected site.
After adjustment, the project had an installed capacity of 200 MW (with the DC side at 258.43 MWp), with 416,832 pieces of 620 Wp monocrystalline silicon modules to be installed. The total land area was 301.42 h㎡. It cancelled 62.67 h㎡ of land parcels within the original EIA land acquisition scope that could not be implemented, continued to use 150.72 h㎡ of the land area from the original EIA, and added 150.7 h㎡ of land area for the PV zone.
The project developer is Guizhou Huadian Lianxin Energy Co., Ltd., a company under Huadian New Energy.
![[SMM PV News Flash] Lincang Tea–PV Complementary Digital Innovation Project Wins National Technology Award](https://imgqn.smm.cn/usercenter/SoBNj20251217171739.jpg)
![[SMM PV Flash] LONGi Again Earned BNEF PV+ESS Dual Tier 1, Continuing to Lead the Global First Tier of New Energy](https://imgqn.smm.cn/usercenter/XNRWp20251217171738.jpg)
![PV aluminum frame operations continue to consolidate on a strong note, aluminum price macro sentiment weakens, and inventory forward oversupply pressure persists [SMM Analysis]](https://imgqn.smm.cn/usercenter/GHTIQ20251217171741.jpg)