[SMM Computing Power Daily] Construction Chaos and Soaring High-End Card Prices: Computing Power Market’s Hot and Cold Overlap

Published: Aug 5, 2026 18:27
On the investment and construction side, the chaos of 'bottom-line contracting' emerged, where some enterprises involved in lawsuits leveraged high registered capital to package their construction capabilities; in South China, 20 units of RTX 5090 eight-card setups without networking were for lease, with a monthly rent of 13,000 yuan per unit; H100 three-year terms including cabinet and electricity were quoted at over 75,000 yuan per month, with downstream acceptance reaching 78,000 yuan per month, while H200 was quoted at 120,000-135,000 yuan per month and rose this week; surplus RTX 4090 stock and intermediary quotations simultaneously rose (7,200-8,000 yuan per unit); 910B2 along with relocation and networking became mainstream demands of operators. The market's structural stratification continued.

SMM, August 5 –

Computing Power Investment and Construction Shows "Guaranteed Construction" Chaos

SMM learned that chaos in the computing power investment and construction segment has gradually emerged: some enterprises with relatively high registered capital but legal disputes have undertaken data center projects on a "guaranteed construction" basis, aiming for completion within one month. Such entities appear financially robust, but compliance and contract fulfillment risks cannot be overlooked. Project sponsors must verify the progress of their disputes and actual construction capabilities to mitigate schedule and funding risks.

20 Non-Networked RTX 5090 8-GPU Servers Available for Lease in South China

SMM learned that a computing power service provider in South China released 20 units of RTX 5090 8-GPU server rental resources, with a monthly rent quoted at 13,000 yuan per unit. These machines were deployed independently without networking, suitable for lightweight scenarios such as distributed inference or rendering. Non-networked configurations offer high flexibility and low barriers to entry, but lack cluster interconnectivity, limiting their suitability for large-scale training and distributed tasks; lessees need to evaluate based on their specific scenarios.

H100/H200 Quotations Fluctuate at Highs, Long-Term Agreements Become Mainstream

SMM understood that three-year H100 rental quotations including cabinets and electricity had exceeded 75,000 yuan/month; downstream acceptance quotations generally reached 78,000 yuan/month. Meanwhile, a certain operator’s internal budget for long-term leases (1-3 years, with relocation and networking) was approximately 63,000-65,000 yuan/month, and an IDC service provider judged that a three-year budget of 62,000 yuan/month was realistically hard to match, highlighting a clear gap between budget and market prices. H200 quotation range stood at 120,000-135,000 yuan/month, and showed an upward trend this week. High-end card prices remained in an upward channel.

RTX 4090 Residual Stock and Intermediary Quotations Rise Together

SMM understood that a smart computing service provider still had dozens of residual RTX 4090 8-GPU machines on hand; the 1TB memory version’s monthly rent of 7,200 yuan was its floor price, while similar 512GB memory versions on the market had risen to 8,000 yuan/month. University-side cloud platforms quoted 7,000 yuan/month externally, and intermediary quotations ranged from 7,400 to 8,000 yuan/month. Overall, consumer-grade card prices edged up slightly, but downstream acceptance prices from universities were low, narrowing profit margins.

Ascend 910B2 Demand and Relocation with Networking Requirements

SMM learned that demand-side buyers for Ascend 910B2 in the Beijing direction were quite interested in a quote of 15,000 yuan/month, with relocation required. Multiple sources reported that operators preferred machines to be moved into their own equipment rooms with networking: one operator’s H100 long-term lease demand required relocation with networking; another operator opened model access and welcomed machines to be relocated to its equipment rooms, preferably with existing main networks retained to save on external purchases; a subsidiary of a certain corporation could undertake H100 relocation; and a cloud service provider, facing tight resources for scattered university rentals, had completed quotation matching for one A100 server.

SMM Analysis: The investment & construction and leasing sides showed diverging trends. On the investment & construction side, capital packaging coexisted with litigation risks, and the "guaranteed construction" model accelerated implementation while amplifying contract fulfillment uncertainties. On the leasing side, quotations for high-end cards (H100/H200) fluctuated at highs, long-term agreements and relocation with networking became mainstream demands of operators; the consumer-grade RTX 5090 expanded supply in a flexible non-networked form; residual RTX 4090 stock and intermediary quotations rose together, though downstream acceptance prices were low. Overall, the structural stratification of the computing power market continued, with risk management, scenario matching, and verification of resource authenticity becoming common key words for both sides.

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
Prysmian scales data-centre cabling for AI infrastructure
10 hours ago
Prysmian scales data-centre cabling for AI infrastructure
Read More
Prysmian scales data-centre cabling for AI infrastructure
Prysmian scales data-centre cabling for AI infrastructure
Data Centre Magazine reported on Aug 27 that Prysmian is rolling out a fibre-plus-copper composite cabling programme for AI data centres, running in parallel with its $1.25 billion three-state US expansion. The programme covers pre-terminated fibre, AOC active optical cable, direct-attach copper (DAC), and rack-level power distribution copper busbars, targeting hyperscale and colocation buyers. The Molex EUR 5.5 billion long-term agreement executes alongside; Prysmian expects North America data-centre fibre:copper cable mix to shift from 60:40 toward 45:55 over 2027-2030, with AI compute nodes driving incremental demand for high-speed differential copper and 800 V busbars.
10 hours ago
[SMM Computing Power News Flash] DSV4-Flash Token Breaches 20% Discount, Resale Spread Nears Zero
11 hours ago
[SMM Computing Power News Flash] DSV4-Flash Token Breaches 20% Discount, Resale Spread Nears Zero
Read More
[SMM Computing Power News Flash] DSV4-Flash Token Breaches 20% Discount, Resale Spread Nears Zero
[SMM Computing Power News Flash] DSV4-Flash Token Breaches 20% Discount, Resale Spread Nears Zero
SMM has learned that a certain MaaS platform is currently selling DeepSeek-V4-Flash model tokens at 78% of DeepSeek's official website price. The sales side also has a policy: "If usage exceeds 30,000 yuan, the official website price is further discounted to 95%." The platform's developers bluntly say that the 95% price may be completely unprofitable. The platform uses a hybrid model of partly self-built deployment and partly access to large vendors' APIs, with large vendors as the upstream. Capacity is expanded whenever usage exceeds the limit, and the TPM ceiling has been raised several times to 30 million. According to its feedback, the discount spread between upstream and downstream in token resale is extremely small, margins are negligible, and profitability is far lower than that of the computing power leasing business.
11 hours ago
[SMM Computing Power Flash] Jinan H20-141G Monthly Rent 52,000 Yuan, 3-Year Lease Intent Under Discussion
11 hours ago
[SMM Computing Power Flash] Jinan H20-141G Monthly Rent 52,000 Yuan, 3-Year Lease Intent Under Discussion
Read More
[SMM Computing Power Flash] Jinan H20-141G Monthly Rent 52,000 Yuan, 3-Year Lease Intent Under Discussion
[SMM Computing Power Flash] Jinan H20-141G Monthly Rent 52,000 Yuan, 3-Year Lease Intent Under Discussion
SMM has learned that a carrier equipment room in Jinan, Shandong currently has one H20-141G complete machine available for lease, with a monthly rent of 52,000 yuan, a one-month deposit and three months' rent paid in advance, test delivery support, 100M dedicated bandwidth at 25 yuan/month and shared bandwidth at 20 yuan/month (12-month term), and line access limited to the carrier's own network. A downstream client of an IDC service provider is interested in leasing the entire unit for a three-year term. The current price is already within the client's budget, and the commercial process is still advancing. SMM believes that for a single-unit H20-141G lease, the process from inquiry to contract signing is relatively long, and after the price is agreed, the transaction pace mainly depends on the client's internal procedures.
11 hours ago