Deep Earthquake Risks Emerge; Codelco Suspends Andes Norte Expansion Project at El Teniente Copper Mine [SMM Analysis]

Published: Aug 5, 2026 14:47
[Deep Seismic Risks Emerge, Codelco Suspends Andes Norte Expansion Project at El Teniente Copper Mine] Codelco temporarily suspended development and construction activities at the Andes Norte project of the El Teniente copper mine due to potential new-type seismic risks emerging in deep areas, while other production areas of the mine remain in operation. The company will further strengthen seismic monitoring and technical assessment and has not yet announced a resumption time. Andes Norte is an important project for the deep resource succession of El Teniente. This suspension may increase uncertainty over the mine’s medium and long-term production recovery and the commissioning of deep projects.

       

       On August 4, Codelco announced a temporary suspension of development and construction activities at the Andes Norte project of its El Teniente copper mine, due to a potential new-type seismic risk in the deep area of the project. This measure applies only to the Andes Norte project and does not entail a full shutdown of the El Teniente mine; other production areas remain operational, with seismic monitoring and related safety measures continuing.

       Codelco stated that data and technical analysis collected over the past six months indicate that, as works advance deeper into the deposit, the Andes Norte area may exhibit a seismic phenomenon distinct from those previously known and managed at the mine. During the suspension, the company will further enhance instrument installation, seismic monitoring, and technical analysis, and will evaluate the project’s subsequent construction arrangements after clarifying and implementing the necessary risk control measures. Currently, Codelco has not announced a specific timeline for resuming construction, and activities of contractors involved in the project development and construction will also be suspended simultaneously.

       Andes Norte, together with Andesita and Diamante, forms the deep development project portfolio of the El Teniente copper mine, aimed at further extending mining activities to the deeper Teniente 9 level. As of the end of 2025, the construction progress of the Andes Norte project was approximately 81%. The entire project portfolio plans to add approximately 2 billion mt of ore reserves, with an average copper grade of about 0.86%, and to support El Teniente in maintaining a daily average ore processing capacity of 137,000 mt, extending the mine life by over 50 years.

       On July 31, 2025, a severe rock burst and tunnel collapse accident occurred near the Andesita project of the El Teniente mine, resulting in the deaths of six workers, after which multiple production and development areas were restricted. Affected by this, El Teniente’s copper production in 2025 fell 13% YoY to 310,000 mt. Codelco had previously expected the mine’s copper production in 2026 to be about 301,000 mt, with output potentially remaining at relatively low levels over the next five years.

      The current suspension of the Andes Norte project is expected not to directly affect the short-term copper production of existing areas at El Teniente, but may further delay the succession of deep resources and the future production recovery process. With the Andesita project still under continuity plan assessment, the renewed suspension of Andes Norte will also increase uncertainty for Codelco in achieving the medium and long-term production recovery targets of El Teniente. Currently, Codelco has not disclosed the potential investment adjustments and additional copper production losses resulting from this suspension.

 

Data Source Statement: Except for publicly available information, all other data are processed by SMM based on publicly available information, market communication, and relying on SMM's internal database model. They are for reference only and do not constitute decision-making recommendations.

For any inquiries or for more information, please contact: lemonzhao@smm.cn
For more information on how to access our research reports, please contact:service.en@smm.cn
Related News
【SMM Flash】Middle East August Sulfur Contract Prices Released
2 hours ago
【SMM Flash】Middle East August Sulfur Contract Prices Released
Read More
【SMM Flash】Middle East August Sulfur Contract Prices Released
【SMM Flash】Middle East August Sulfur Contract Prices Released
KPC has set the August Kuwait Sulphur Price (KSP) at $865/mt FOB, down by $85/mt from the July KSP of $950/mt; QatarEnergy has kept its August Qatar Sulphur Price (QSP) unchanged at $890/mt FOB from July; ADNOC has kept its August official selling price (OSP) for the Indian subcontinent unchanged at $1,000/mt FOB Ruwais from July.
2 hours ago
Khoemacau Copper Mine Boosts Q2 2026 Output, Expansion On Track
3 hours ago
Khoemacau Copper Mine Boosts Q2 2026 Output, Expansion On Track
Read More
Khoemacau Copper Mine Boosts Q2 2026 Output, Expansion On Track
Khoemacau Copper Mine Boosts Q2 2026 Output, Expansion On Track
Botswana's Khoemacau copper mine increased copper production in the second quarter of 2026 as improved ore grades offset lower mining volumes, while construction of its major expansion project continued to advance. According to MMG Limited's second-quarter production report, Khoemacau produced 11,423 tonnes of copper in concentrate during the three months ended 30 June, representing a 7% increase from the previous quarter and remaining broadly in line with production achieved in the corresponding period of 2025. Although ore milled declined year-on-year, the operation benefited from improved copper grades of 1.62%, up from 1.59% a year earlier, as mining progressed into higher-grade sections of the Zone 5 orebody. Metallurgical recovery remained stable at 88.2%. MMG said lower ore mined volumes reflected earlier development delays and reduced equipment availability. However, the company expects operational performance to strengthen during the second half of 2026 as new mining equipment is deployed, refurbished fleet units are commissioned, and access to higher-grade mining areas continues. The company maintained its 2026 copper production guidance of 48,000-53,000 tonnes while lowering C1 cash cost guidance to US$1.70-US$2.00/lb, supported by stronger silver prices. Construction of Khoemacau's expansion project also progressed during the quarter. The project is designed to increase annual copper production to 130,000 tonnes of copper in concentrate and more than 4 million ounces of silver, with first concentrate expected in the first half of 2028. Continued progress at Khoemacau reinforces Botswana's position as an emerging copper producer at a time of tightening global supply. The expansion is expected to add meaningful new copper capacity over the medium term, supporting long-term supply growth as demand from electrification, renewable energy and electric vehicle manufacturing continues to accelerate.
3 hours ago
Data: SHFE, DCE market movement (Aug 05)
4 hours ago
Data: SHFE, DCE market movement (Aug 05)
Read More
Data: SHFE, DCE market movement (Aug 05)
Data: SHFE, DCE market movement (Aug 05)
The following table shows the ferrous and nonferrous metals movement on the SHFE and DCE on 05 Aug , 2026
4 hours ago
Register to Continue Reading
Gain access to the latest insights in metals and new energy
Already have an account?Sign in here
Deep Earthquake Risks Emerge; Codelco Suspends Andes Norte Expansion Project at El Teniente Copper Mine [SMM Analysis] - Shanghai Metals Market (SMM)